When a project is classified as resource-constrained, a resource constraint exists, and positive slack is insufficient, then the project duration is typically __________.
Multiple Choice
without slack
fixed
extended
flexible
static
Ans. Extended.
The project duration is typically extended because the resource-constrained project is a scheduling problem. It is evaluated as a lack of resources by limited activities and availability. If in a project resource, labor availability and positive slack are insufficient, then it will extend the project completion schedule and continue the program of the project processes because these are the main component for project completion at a scheduled time.