In reviewing the status of a project with top management, a team leader was told that there are only two programmers that can be used for the project. The project is classified as __________ constrained.
Multiple Choice
time
quality
cost
performance
resource
The project is classified as (e) Resource constrained.
The Resource Constrained Project is the Scheduling Issue subclass that deals with situations when the workers or employees working to execute the jobs are constrained and each job has an arrival deadline, a due date and a delay-related cost. In a resource-constrained project, operation with the shortest length is typically granted second preference in distributing resources.
Scheduling projects categorized as resource constrained concentrate on finishing the project as early as possible. For one person too many concurrent operations are an example of Resource constraint.