Question

A Northern British Columbia lumberyard has four jobs on order, as shown in the following table....

A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule.

Job Due Date Remaining Time (Days)
A 212 6
B 209 3
C 214 10
D 210 8

In what sequence would the jobs be ranked according to the following decision rules:

a) FCFS

b) SPT

c) LPT

d) EDD

e) Critical ratio

Which is best and why? Which has the minimum lateness?

Homework Answers

Answer #1

a)

Using FCFS decision rule, the order of jobs is as follows –

Sequence

Job

1

A

2

B

3

C

4

D

Job Sequence

Processing Time

(in Days)

Due Date

(Days remaining)

Flow Time

(in Days)

Days Late = Flow Time - Due Date

(in Days) (0 if negative)

A

6

212 – 205 = 7

0 + 6 = 6

0

B

3

209 – 205 = 4

6 + 3 = 9

5

C

10

214 – 205 = 9

9 + 10 = 19

10

D

8

210 – 205 = 5

19 + 8 = 27

22

Total

27

61

37

Average lateness using FCFS rule = Days Late / Total Number of Jobs = 37 / 4 = 9.25 days.

b)

Using SPT decision rule, the order of jobs is as follows –

Sequence

Job

1

B

2

A

3

D

4

C

       

Job Sequence

Processing Time

(in Days)

Due Date

(Days remaining)

Flow Time

(in Days)

Days Late = Flow Time - Due Date

(in Days) (0 if negative)

B

3

4

0 + 3 = 3

0

A

6

7

3 + 6 = 9

2

D

8

5

9 + 8 = 17

12

C

10

9

17 + 10 = 27

18

Total

27

56

32

Average lateness using SPT rule = Days Late / Total Number of Jobs = 32 / 4 = 8 days.

c)

Using LPT decision rule, the order of jobs is as follows –

Sequence

Job

1

C

2

D

3

A

4

B

Job Sequence

Processing Time

(in Days)

Due Date

(Days remaining)

Flow Time

(in Days)

Days Late = Flow Time - Due Date

(in Days) (0 if negative)

C

10

9

0 + 10 = 10

1

D

8

5

10 + 8 = 18

13

A

6

7

18 + 6 = 24

17

B

3

4

24 + 3 = 27

23

Total

27

79

54

Average lateness using LPT rule = Days Late / Total Number of Jobs = 54 / 4 = 13.50 days.

d)

Using EDD decision rule, the order of jobs is as follows –

Sequence

Job

1

B

2

D

3

A

4

C

    

Job Sequence

Processing Time

(in Days)

Due Date

(Days remaining)

Flow Time

(in Days)

Days Late = Flow Time - Due Date

(in Days) (0 if negative)

B

3

4

0 + 3 = 3

0

D

8

5

3 + 8 = 11

6

A

6

7

11 + 6 = 17

10

C

10

9

17 + 10 = 27

18

Total

27

58

34

Average lateness using EDD rule = Days Late / Total Number of Jobs = 34 / 4 = 8.5 days.

(e) Critical ratio.

Job

Remaining Job Time

(in Days)

Due Date

(Days remaining)

Critical ratio = (Remaining time until due date) / (Remaining job time)

Priority

A

6

7

7 / 6 = 1.17

3

B

3

4

4 / 3 = 1.33

4

C

10

9

9 / 10 = 0.9

2

D

8

5

5 / 8 = 0.625

1

So the job sequence = D – C – B – A.

Job Sequence

Processing Time

(in Days)

Due Date

(Days remaining)

Flow Time

(in Days)

Days Late = Flow Time - Due Date

(in Days) (0 if negative)

D

8

21

0 + 8 = 8

3

C

10

16

8 + 10 = 18

9

A

6

15

18 + 6 = 24

17

B

3

17

24 + 3 = 27

23

Total

27

77

52

Average lateness using Critical Ratio rule = Days Late / Total Number of Jobs = 52 / 4 = 13 days.

Here SPT decision rule is the best as it has minimum lateness, i.e., 8 days.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following jobs have arrived in order. Job Time Due Date 1 4 15 2 7...
The following jobs have arrived in order. Job Time Due Date 1 4 15 2 7 16 3 2 8 4 6 21 5 3 9 If we are interested in Job Lateness as a measure, is SPT or FCFS the better sequencing method to use? If we are interested in Flow Time as a measure, is SPT or FCFS the better sequencing method to use?
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job...
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job A, Process time =14 days, and due date November 26 Job B, Process time= 11 days, and due date = November 25 Job C, Process time =7 days, and due date= December 14 Job D, Process time=6 days, and due date= November 29 Job E, Process time= 2 days, and due date= November 20 Schedule the jobs according to SPT. What are the average...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.] Five jobs arrived to be processed with the processing times and due dates. Present Date= 300 Work Order A B C D E Processing Times (Days) 14 5 40 12 7 Due Date 167 163 195 191 161 . . . Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Processing Due Job Time (days) Date (Days) W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in his shop today? A. 0 B. 1 C. 2 D. 3 E. 4
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
What role could the governance of ethics have played if it had been in existence in...
What role could the governance of ethics have played if it had been in existence in the organization? Assess the leadership of Enron from an ethical perspective. THE FALL OF ENRON: A STAKEHOLDER FAILURE Once upon a time, there was a gleaming headquarters office tower in Houston, with a giant tilted "£"' in front, slowly revolving in the Texas sun. The Enron Corporation, which once ranked among the top Fortune 500 companies, collapsed in 2001 under a mountain of debt...
Discuss ethical issues that can be identified in this case and the mode of managing ethics...
Discuss ethical issues that can be identified in this case and the mode of managing ethics Enron finds itself in this case. How would you describe the ethical culture and levels of trust at Enron? Provide reasons for your assessment. THE FALL OF ENRON: A STAKEHOLDER FAILURE Once upon a time, there was a gleaming headquarters office tower in Houston, with a giant tilted "£"' in front, slowly revolving in the Texas sun. The Enron Corporation, which once ranked among...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...