The following table lists the components needed to assemble an
end item, lead times (in weeks), and quantities on hand.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
I got 442 for part 'a.' which was incorrect. This is what I primarily need help with.
(a)
L = 2*43 = 86
Available L =8. So Net requirement of L = 78
==============================================
C = 1*43 = 43
Available C = 12
Net requirement = 43 – 12 = 31
==============================================
K = 3 * 43 = 129
Available K = 17
Net requirement = 129 – 17 = 112
===============================================
B = 2L+2C+2K = 2*78 + 2*31 + 2*112 = 156+62+224 = 442
Available B = 32
Net requirement = 442 – 32 = 410
Hope this will help. Thank you. Please do not forget to upvote if you find the answer helpful.