Question

Consider the simple 3-station assembly line illustrated below, where the 2 machines at Station 1 are...

Consider the simple 3-station assembly line illustrated below, where the 2 machines at Station 1 are parallel, i.e., the product only needs to go through one of the 2 machines before proceeding to Station 2.

What is the bottleneck time of this process? Convert to time from units.

A.

12 minutes

B.

20 minutes

C.

6 minutes

D.

38 minutes

E.

10 minutes

Homework Answers

Answer #1

Station 1, Machine 1 capacity = 3 units per hour

Cycle time = 60/3 = 20 minutes

Station 1, Machine 2 capacity = 3 units per hour

Cycle time = 60/3 = 20 minutes

Average cycle time for station 1 = 60/6 = 10 minutes

Now,

Capacity for station 2 = 5 units per hour

Cycle time for station 2 = 60/5 = 12 minutes

Capacity for station 3 = 10 units per hour

Cycle time for station 3 = 60/10 = 6 minutes

Highest cycle time in the system is the bottleneck time which is 12 minutes.

Hence, Option A. 12 minutes is correct answer.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Four Step Process with Rework and Scrap Consider the following four step assembly operation with quality...
Four Step Process with Rework and Scrap Consider the following four step assembly operation with quality problems. All resources are staffed with one operator. -The first resource has a processing time of 4 minutes per unit -The second resource has a processing time of 3 minutes per unit. This process suffers from a high yield loss and 50% of all products have to be scrapped after this step. -The third resource also suffers from quality problems. However, instead of scrapping...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 100 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 120 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
Consider a simple series RLC circuit with the following values for the resistance, inductance, and capacitance:...
Consider a simple series RLC circuit with the following values for the resistance, inductance, and capacitance: R = 110 Ω (ohms), L = 1 H (henries), and C = 0.001 F (farads). Furthermore, a battery provides an external voltage, e(t), into the circuit equal to 7 However, this external voltage e(t) is not always flowing into the circuit. Initially, the switch for the circuit is open and there is no charge or current flowing through the circuit. At time t...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of a specific product in the past three years. Quarter Year 1 2 3 4 2015 350 254 176 228 2016 367 258 169 236 2017 342 250 166 228 Predict demand in quarter 1 and quarter 2 of 2018, given that the demand forecast for the whole year is a total of 1,040 units. Question 6: DRP (8 p) A central DC supplies a...
Case Study 7-2 FIVE STAR TOOLS Five star tools is a small family -owned firm that...
Case Study 7-2 FIVE STAR TOOLS Five star tools is a small family -owned firm that manufactures diamond -coated cutting tools( chisels and saws) used by jewelers. Production involves three major processes. First, steel “ blanks” (tools without the diamond coating) are cut to size. Second, the blanks are sent to a chemical bath that prepares the tools for the coating process. In the third major process, the blanks are coated with diamond chips in a proprietary process that simultaneously...
Identify hidden cost Identify a sunk cost trap Another assembly line is under construction in Building...
Identify hidden cost Identify a sunk cost trap Another assembly line is under construction in Building 3, to make a new stainless-steel dishwasher starting in early 2013. Building 1 is getting an assembly line to make the trendy front-loading washers and matching dryers Americans are enamored of; GE has never before made those in the United States. And Appliance Park already has new plastics-manufacturing facilities to make parts for these appliances, including simple items like the plastic-coated wire racks that...
1. Read the article and discuss how operations can provide strategic advantage to this organisation. 2....
1. Read the article and discuss how operations can provide strategic advantage to this organisation. 2. Discuss the performance of the company in terms of the five performance objectives and the relationship among these performance objectives. 3. Discuss a suitable operations strategy approach for these kinds of organisations. Operations Strategy in Action Almost every company seems to be restructuring itself to face the downturn, be it through financial engineering, or by retrenching to core activities. So they sell off foreign...
Do the following problems. 1. Each of three barrels from a manufacturing line are classified as...
Do the following problems. 1. Each of three barrels from a manufacturing line are classified as either above (a) or below (b) the target weight. Provide the ordered sample space. 2. The heat on each of two soldered parts is measured and labeled as either low (l), medium (m), or high (h). State the number of elements in the ordered sample space. 3. Consider the set of Beatles songs with a primary writer as either Paul McCartney (P) or John...
for the scenario below: 1) Apply the qualitative analysis by identifying at least 3 issues in...
for the scenario below: 1) Apply the qualitative analysis by identifying at least 3 issues in the above process. Analyse these issues by using a. Adding-value and Waste Analysis b. Issue register, If you find that there are more than three issues, you can focus on the three issues that have the highest impact. 2). Calculate the cycle time efficiency of the as-is process. You can assume a working week of 40 hours. In case there is missing information, you...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT