Activity |
Duration (days) |
Predecessors |
Resources |
A |
5 |
- |
Jane |
B |
7 |
A |
Marry, Kate |
C |
3 |
A |
Dennis |
D |
3 |
B |
Kate |
E |
8 |
D |
William |
F |
10 |
C |
Sam |
G |
8 |
F |
William |
H |
3 |
E, G |
Jane |
1. Draw the network diagram and indicate the critical path.
2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks.
3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a MS Project file.
4. Eliminate the problem of resource overallocation on MS Project, and indicate the impact of this action.
Answer: Pleas refer below details for network diagram, Critical path and resource leveling for the given case.