Today is Nov. 16. The following jobs need to be scheduled on the same machine.
Job A, Process time =14 days, and due date November 26
Job B, Process time= 11 days, and due date = November 25
Job C, Process time =7 days, and due date= December 14
Job D, Process time=6 days, and due date= November 29
Job E, Process time= 2 days, and due date= November 20
Schedule the jobs according to SPT. What are the average lateness for the SPT Schedule?