Question

#3) Planned duration of a project is 28 weeks. Budget at completion for the project is...

#3) Planned duration of a project is 28 weeks. Budget at completion for the project is $525,000. The project is in its 25th week. The actual cost (thus far) is $270,000. At this point in the plan, the planned cost was expected to be $261,000. For the work performed to date, the earned value is estimated at $272,000. Compute the following for the project (10 points) a) Cost variance. b) Schedule variance. c) If rest of the project is assumed to be completed at the current cost performance level, compute estimated total cost at completion of the project. d) If rest of the project is assumed to be completed at the current schedule performance level, compute estimated project completion time.

Homework Answers

Answer #1

BAC = 525,000

Actual cost, (AC) = 270,000

Planned Value (PV) = 261,000

Earned Value (EV) = 272,000

a) Cost Variance = EV - AC = 272000 - 270000 = 2,000

b) Schedule Variance = EV - PV = 272000 - 261000 = 11,000

c) Cost Performance Index, CPI = EV/AC = 272000/270000 = 1.0074

Estimate At Completion (EAC) = AC + (BAC - EV)/CPI = 270000 + (525000 272000)/1.0074 = $ 521,142

d)

Planned Duration, PD = 28 weeks

Actual Time, AT = 25 weeks

Earned Schedule, ES = not given

Therefore, Estimated Completion Date (ECD) cannot be determined in absence of information about Earned Schedule (ES)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent...
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent Completed A 3.00 - 15000 1.00 B 1.00 A 5000 0.00 C 2.00 A 10000 1.00 D 3.00 A 21000 0.50 E 2.00 B,C 32000 0.00 F 1.00 C 5000 0.00 G 1.00 C 5500 0.00 The project started on June 1st. The project has a planned duration of 7 months. Data below are planned cost and actual cost (spent) from June to November:...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Your project has a total budget of $10,000,000. At the end of week 26 of your...
Your project has a total budget of $10,000,000. At the end of week 26 of your project, you have the following values: Planned Value: $1,000,000 Earned Value: $750,000 Actual Cost: $1,250,000 Questions: What is your schedule variance? Is your project ahead of or behind schedule? What is your cost variance? Is your project over budget or under budget? Provide two estimates of the cost at completion for your project. Be sure to show your calculations.
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the...
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the following schedule and cost estimate. What is the budget at completion (BAC) for Ralph’s garage? At the end of week 1, the contractor completed 80% of the footing, framing, and siding. He spent 3,000 on concrete, lumber and vinyl siding. He also paid 1,500 in wages to laborers to complete the footing, framing, and siding. what is the earned value (EV) for Task A...
Your project to obtain charitable donations is now 48 days into a planned 58-day project. The...
Your project to obtain charitable donations is now 48 days into a planned 58-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 44 days of the project and to bring in $24,600. Even though we are 48 days into the project, we still see that we have only 90% of this activity complete. The second activity relates to company donations and is scheduled to...
When looking at the life of a project plan, it is useful to graph and outline...
When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project. Execise#2: 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative completed times for four periods of the project. Completed% Activity ID Activity Predecessors Estimated Duration(Weeks) Budget ($) Actual Spend ($) 1 2 3 4 Crash time Crash cost$ A 7          7,000                       9,000 20 40 100 100 6             8,000 B A 2          5,000                       5,000 20 60 100 100 1             7,000 C A 4          9,000                       6,000 0 40...
The project is estimated to be of 10 years duration. It involves setting up new machinery...
The project is estimated to be of 10 years duration. It involves setting up new machinery with an estimated cost of as much as Thai baht (THB) 375 million, including installation. This amount could be depreciated using the straight-line method (SLM) over a period of 10 years with a resale value of THB13.5 million. The project would require an initial working capital of THB 15.5 million. With the planned new capacity, the company would be able to produce 60,000 pieces...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...