Question

In a furniture manufacturing facility, the daily demand to quick-dry glue is normally distributed with a...

In a furniture manufacturing facility, the daily demand to quick-dry glue is normally distributed with a
constant average of 5 kg. and constant standard deviation 1. The manufacturer procures the glue from a
glue supplier. Both facilities work on a 24/7 basis. The fixed ordering cost is $60 per order. While keeping
the glue in inventory for one hour, maintaining the adhesiveness of one kilogram costs $0.01. Since it is
an important component of the furniture products, a shortage in glue is not a desirable situation.
(a) In the beginning, it was told that the lead time of the glue supplier is constant and 4 days from order to
delivery. Suppose the probability of glue shortage is allowed to be 0.005 at maximum. What should be
the safety stock level and what is the optimal inventory policy? Carry out the whole analysis
and show all of your calculations.
(b) Later, it is realized that there were some issues with the delivery reliability of the glue supplier. The
lead time was actually normally distributed with a constant average of 4 days and constant variance
0.20. Suppose the maximum probability of glue shortage is reduced to 0.001. Assuming independence
between the demand and the lead time, what should be the safety stock level and what is the optimal
inventory policy? Carry out the whole analysis and show all of your calculations.

Homework Answers

Answer #1

The daily average demand is given as 5Kg.Therefore,

Mean of glue required daily(µ) = 5 Kg

Std. deviation of glue required(σ) = 1 Kg

(a)

As given in question, the maximum glue shortage allowed is 0.005.

Therefore the confidence interval is 99.5%.[ 1-0.005= 0.995 or 99.5%]

The z value for 99.5% confidence interval is 2.807  

Let the maximum daily usage of glue be x.

Then using the formulae: (x-µ)/σ = z-value

We put the values to find x: (x-5)/1= 2.807

x=7.807 Kg

Safety stock= (Maximum Daily usage*Maximum lead time)-(Average Daily usage*Average lead time)

Safety Stock= (7.807*4)-(5*4)= 11.228 Kg

Note:- In part (a) maximum lead time is same as average lead time.

Optimum Inventory policy:

Economic Order Quantity

EOQ= (2AO/H)1/2

Where A= Average daily usage in Kg= 5

O= Ordering cost= 60$

H= Holding cost/ Kg daily= 24*0.01= 0.24 $/Kg per day

EOQ= (2*5*60/.24)1/2 = 50 Kg

Re-order point= (Lead time* Average daily usage) + Safety stock

Re-order point= (4*5) + 11.228= 31.228 Kg.

(b)

As next part, the maximum glue shortage allowed is 0.001.

Therefore the confidence interval is 99.9%.[ 1-0.001= 0.999 or 99.9%]

The z value for 99.5% confidence interval is 3.291  

Let the maximum daily usage of glue be x1.

Then using the formulae: (x1-µ)/σ = z-value

We put the values to find x1: (x1-5)/1= 3.291

x1=8.291 Kg

Similarly we calculate maximum lead time.

Let the maximum lead time be x2

µ (Mean Time)= 4 days

σ ( Standard deviation)= .2

The confidence interval is 99.9%. The z value for 99.5% confidence interval is 3.291

using the formulae: (x2-µ)/σ = z-value (Where x= maximum lead time)

We put the values to find x: (x2-4)/.2= 3.291

x2= 4.6582

Safety stock= (Maximum Daily usage*Maximum lead time)-(Average Daily usage*Average lead time)

New Safety Stock= (8.291*4.6582)-(5*4)= 18.6211 Kg

Optimum Inventory policy:

EOQ= (2*5*60/.24)1/2 = 50 Kg [ It remains same]

Re-order point= (Lead time* Average daily usage) + Safety stock

Re-order point= (4*5) + 18.6211= 38.6211 Kg.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Daily demand for neckties at a MegaMart store is normally distributed with a mean of 20...
Daily demand for neckties at a MegaMart store is normally distributed with a mean of 20 units and a standard deviation of 7. The supplier, Suits Galore, takes on average about 9 days to supply a MegaMart order. The standard deviation of lead time is 3 days. MegaMart is targeting a customer service level of 95 percent (z = 1.65) and monitors its inventory continuously. How much safety inventory of neckties should MegaMart carry? What should their reorder point (ROP)...
Question 1: Daily demand for ground coffee at a Whole Foods store is normally distributed with...
Question 1: Daily demand for ground coffee at a Whole Foods store is normally distributed with a mean of 100 pounds (lbs) and a standard deviation of 50 pounds. Store manager continuously monitors the inventory of coffee and currently orders 1,000 lbs of coffee each time the inventory drops to 410 lbs. Whole Foods’s coffee supplier BlackBean takes 4 days to fill an order. (a): How much safety inventory does the store carry with the current inventory policy? (b): What...
Daily demand for a certain product is normally distributed, with a mean of 200 and a...
Daily demand for a certain product is normally distributed, with a mean of 200 and a standard deviation of 25. The supplier is reliable and maintains a constant lead time of 4 days. The cost of placing an order is $10 and the cost of holding inventory is $0.50 per unit per year. Consider service level of 90%. What is the required safety stock? a.) 64 b.) 85 c.) 75 d.) 54 What is the reordering point? 864 762 575...
(a) The demand for item X is estimated to be normally distributed with a mean demand...
(a) The demand for item X is estimated to be normally distributed with a mean demand of 300 units per day and a standard deviation of 20 units per day. What is the reorder point and safety stock under continuous review policy? (Assume 95% service level, z (0.95) =1.65) (b) The supplier has changed. All costs remain the same, but lead time changes from 3 days to 30 days.What would be the new reorder point and safety stock? What do...
Weekly demand for Canon printers at a BestBuy store is normally distributed with a mean of...
Weekly demand for Canon printers at a BestBuy store is normally distributed with a mean of 250 and a standard deviation of 80. Inventory is continuously monitored and an order of 1,000 printers is placed each time the inventory drops to 950 printers. The replenishment lead-time is three weeks. How much safety inventory does the store carry? What is the CSL? Assume that the supply lead-time from Canon is normally distributed with a mean of 3 weeks and a standard...
An inventory item of XYZ Manufacturing has an average daily demand of 10 units with a...
An inventory item of XYZ Manufacturing has an average daily demand of 10 units with a maximum daily demand of 12 units. The economic order quantity is 200 units. Without safety stocks, the reorder point is 50 units. Safety stocks are set at 94 units. Required: a. Determine the reorder point with safety stocks. b. Determine the maximum inventory level. c. Determine the average lead time. d. Determine the maximum lead time
Weekly demand for the latest TV set at a retailer is normally distributed with a mean...
Weekly demand for the latest TV set at a retailer is normally distributed with a mean of 600 TVs and a standard deviation of 150. Currently, the store places orders to the supplier with a reorder point of 1,500 Tvs. Replenishment lead time is 2 weeks, fixed order cost per order is $200, each TV the retailer $300, and the inventory holding cost is 25% per year. If the retailer wants to achieve a 99% service level (use the z-value...
1) Greg Fletcher, the materials manager at Easy Furniture Inc., is responsible for managing the inventory...
1) Greg Fletcher, the materials manager at Easy Furniture Inc., is responsible for managing the inventory of writing desks. Greg isn't talkative about his inventory, but you have managed to extract the following information from him: It costs $35 to place an order. Each writing desk costs $31.33. Annual per unit holding cost is 30%of item value. Average daily demand is 100 writing desks. Standard deviation of demand during lead time is 51.96. Lead time to receive a writing desk...
The daily demand for 60” flat-screen TVs at the Sterling Archer’s discount warehouse is normally distributed...
The daily demand for 60” flat-screen TVs at the Sterling Archer’s discount warehouse is normally distributed with a mean of 5 units and a standard deviation of 5 units. The lead time for receiving a shipment of new TVs is 10 days and is fairly consistent. Determine the reorder point and safety stock for service levels of 90%, 95%, and 98%.
You manage inventory for your company and use a continuous review inventory system to control reordering...
You manage inventory for your company and use a continuous review inventory system to control reordering items for stock. Your company is open for business 300 days per year. One of your most important items experiences demand of 20 units per day, normally distributed with a standard deviation of 3 units per day. You experience a lead time on orders from your supplier of six days with a standard deviation of two days. The unit price, regardless of order size,...