You have the following information on four jobs. Today is the beginning of day 1, so you can assume that the Time needed = work remaining and Due (days) = time remaining.
Job | Time Needed (days) | Due (days) |
P | 8 | 8 |
Q | 10 | 23 |
R | 3 | 17 |
S | 6 | 30 |
T | 4 | 29 |
U | 7 | 24 |
1. If you order these jobs by Shortest Process Time rule, the order will be:
2. If you order these jobs by Earliest Due Date rule, the order will be:
3. What is the Average Flow Time if the jobs are scheduled using the Shortest Processing Time rule:
1) Scheduling by Shortest Processing Time (SPT) rule, the order will be in the ascending order of Time needed.
The order will be: R-T-S-U-P-Q
2) Scheduling by Earliest Due Date (EDD) rule, the order will be in the ascending order of Due time.
The order will be: P-R-Q-U-T-S
3)
Job | Time Needed (days) | Due (days) | Flow Time |
R | 3 | 17 | 3 |
T | 4 | 29 | 7 |
S | 6 | 30 | 13 |
U | 7 | 24 | 20 |
P | 8 | 8 | 28 |
Q | 10 | 23 | 38 |
Flow time = Time needed for previous job + Time needed for current job
Average flow time = (3+7+13+20+28+38)/6 = 109/6 = 18.17 days