Question

You have the following information on four jobs. Today is the beginning of day 1, so...

You have the following information on four jobs. Today is the beginning of day 1, so you can assume that the Time needed = work remaining and Due (days) = time remaining.

Job Time Needed (days) Due (days)
P 8 8
Q 10 23
R 3 17
S 6 30
T 4 29
U 7 24

1. If you order these jobs by Shortest Process Time rule, the order will be:

2. If you order these jobs by Earliest Due Date rule, the order will be:

3. What is the Average Flow Time if the jobs are scheduled using the Shortest Processing Time rule:

Homework Answers

Answer #1

1) Scheduling by Shortest Processing Time (SPT) rule, the order will be in the ascending order of Time needed.

The order will be: R-T-S-U-P-Q

2) Scheduling by Earliest Due Date (EDD) rule, the order will be in the ascending order of Due time.

The order will be: P-R-Q-U-T-S

3)

Job Time Needed (days) Due (days) Flow Time
R 3 17 3
T 4 29 7
S 6 30 13
U 7 24 20
P 8 8 28
Q 10 23 38

Flow time = Time needed for previous job + Time needed for current job

Average flow time = (3+7+13+20+28+38)/6 = 109/6 = 18.17 days

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Processing Due Job Time (days) Date (Days) W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in his shop today? A. 0 B. 1 C. 2 D. 3 E. 4
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job...
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job A, Process time =14 days, and due date November 26 Job B, Process time= 11 days, and due date = November 25 Job C, Process time =7 days, and due date= December 14 Job D, Process time=6 days, and due date= November 29 Job E, Process time= 2 days, and due date= November 20 Schedule the jobs according to SPT. What are the average...
Five jobs are ready for processing at time zero through a workstation. The details of the...
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 5 11 B 6 16 C 3 19 D 4 10 E 2 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is:
The owner/operator of the local franchise of Handyman, Inc. has 4 jobs to complete today, shown...
The owner/operator of the local franchise of Handyman, Inc. has 4 jobs to complete today, shown in the order in which they were received. Job Processing Time (hrs) Due (hrs from now) W 4 4 X 3 5 Y 2 2 Z 1 1 If he or she uses the earliest due date first priority rule to schedule these jobs, what will be the average tardiness?
If the following jobs are sequenced according to the SLACK rule then job A would be...
If the following jobs are sequenced according to the SLACK rule then job A would be completed on day (assume zero for today's date) Job - Processing Time (days) - Due Date A 8 12 B 6 15 C 11 17 D 7 10 E 3 8 Select one: A. 7. B. 15. C. 8. D. 12.
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.] Five jobs arrived to be processed with the processing times and due dates. Present Date= 300 Work Order A B C D E Processing Times (Days) 14 5 40 12 7 Due Date 167 163 195 191 161 . . . Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the...
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table....
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule. Job Due Date Remaining Time (Days) A 212 6 B 209 3 C 214 10 D 210 8 In what sequence would the jobs be ranked according to the following decision rules: a) FCFS b) SPT c) LPT d) EDD e) Critical ratio Which is best and why? Which has the minimum lateness?
The following jobs have arrived in order. Job Time Due Date 1 4 15 2 7...
The following jobs have arrived in order. Job Time Due Date 1 4 15 2 7 16 3 2 8 4 6 21 5 3 9 If we are interested in Job Lateness as a measure, is SPT or FCFS the better sequencing method to use? If we are interested in Flow Time as a measure, is SPT or FCFS the better sequencing method to use?
You have been asked to sequence the following jobs. Task A must always be done before...
You have been asked to sequence the following jobs. Task A must always be done before Task B. Using Johnson's Rule, in what order will you do the jobs? Job Task A Task B A 3 6 B 7 6 C 5 2 D 5 8 E 4 7 F 9 3 G 1 4
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT