Question

The university IT team is working on the implementation of a new software system for enrollment.  Using...

The university IT team is working on the implementation of a new software system for enrollment.  Using the following table, complete the requested tasks:
Activity Immediate Predecessor Normal Crash Normal Crash
A - 6 5 $900 $1,000
B A 8 6 $300 $400
C A 4 3 $500 $600
D B 5 3 $900 $1,200
E C, D 8 5 $1,000 $1,600
a. Draw the network diagram noting normal and crash times.

b. What is the critical path?

c. What is the minimum cost of crashing the project by 4 days? Would you recommend the team crash the project? Explain your calculations and position.

Homework Answers

Answer #1

There are two chains in the following network:

ABDE = 27

ACE = 18

CRITICAL PATH = ABDE = 27


WE WILL ONLY CRASH ACTIVITIES FROM THE CRITICAL PATH IN ORDER TO BRING CHANGES TO THE PROJECT SCHEDULE


CRASHING

CRASH COST PER PERIOD = (CRASH COST - NORMAL COST) / (NORMAL TIME - CRASH TIME)

ACTIVITY

NORMAL TIME

CRASH TIME

NORMAL COST

CRASH COST

COST / PERIOD

TIMES CRASHED

# CRASH

CRASH COST

A

6

5

900

1000

100

1

3RD

100

B

8

6

300

400

50

2

1ST AND 2ND

100

C

4

3

500

600

100

0

D

5

3

900

1200

150

1

4TH

150

E

8

5

1000

1600

200

0

TOTAL COST

3600

350

MIN COST OF CRASHING BY 4 PERIODS = 350

** Leaving a thumbs-up would really help me out. Let me know if you face any problems.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs — 13 8 30 130 B Order equipment A 9 6 120...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
Given the data table below develop the precedence network and perform the CPM calculations. Then, using...
Given the data table below develop the precedence network and perform the CPM calculations. Then, using the proposed crashing strategy calculate the normal, least-cost, and crash duration for the project below. Calculate the cost associated with each duration. Indirect cost (overhead) is $120 per day. Activity IPA Duration Cost $ Normal Crash Normal Crash A - 5 4 $770 $900 B - 3 2 $660 $700 C A 7 4 $800 $1,070 D A,B 4 3 $1,000 $1,110 E B...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following​ table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessors(s) A 4 3 $2,200 $2,850 --- B 2 1 $2,100 $2,700 --- C 3 3 $750 $750 --- D 8 4 $2,500 $2,800 A E 6 3 $800 $1,250...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A — 4 1 5,000 8,000 B — 5 3 8,000 10,000 C A 1 1 4,000 4,000 D B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F D 7 6 4,000 7,000 You are the manager of a project to improve a billing process at your firm. Table 3 contains the data you will need to conduct a cost analysis...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Question 03. Using the information in the table below, assuming that the project team will work...
Question 03. Using the information in the table below, assuming that the project team will work a standard working week (5 working days in a week) and that all tasks will start as soon as possible: Task Description Duration (Working days) Predecessor/s A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D telecoms 15 B E Hardware installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training/Support 5 G I...
Swimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists...
Swimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before Memorial Day weekend (pool opening weekend). You would like to find the minimum cost schedule for your project. There is a $9,000 per week penalty for each week the project is delayed beyond week 9. In addition, your project team determined that indirect costs are $15,000 per week. ACTIVITY Immediate Predecessor (s)...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT