The university IT team is working on the implementation of a new software system for enrollment. Using the following table, complete the requested tasks: |
Activity | Immediate Predecessor | Normal | Crash | Normal | Crash | |||
A | - | 6 | 5 | $900 | $1,000 | |||
B | A | 8 | 6 | $300 | $400 | |||
C | A | 4 | 3 | $500 | $600 | |||
D | B | 5 | 3 | $900 | $1,200 | |||
E | C, D | 8 | 5 | $1,000 | $1,600 | |||
a. Draw the network diagram noting normal and crash times. |
b. What is the critical path?
c. What is the minimum cost of crashing the project by 4 days? Would you recommend the team crash the project? Explain your calculations and position. |
There are two chains in the following network:
ABDE = 27
ACE = 18
CRITICAL PATH = ABDE = 27
WE WILL ONLY CRASH ACTIVITIES FROM THE CRITICAL PATH IN ORDER TO BRING CHANGES TO THE PROJECT SCHEDULE
CRASHING
CRASH COST PER PERIOD = (CRASH COST - NORMAL COST) / (NORMAL TIME - CRASH TIME)
ACTIVITY |
NORMAL TIME |
CRASH TIME |
NORMAL COST |
CRASH COST |
COST / PERIOD |
TIMES CRASHED |
# CRASH |
CRASH COST |
A |
6 |
5 |
900 |
1000 |
100 |
1 |
3RD |
100 |
B |
8 |
6 |
300 |
400 |
50 |
2 |
1ST AND 2ND |
100 |
C |
4 |
3 |
500 |
600 |
100 |
0 |
||
D |
5 |
3 |
900 |
1200 |
150 |
1 |
4TH |
150 |
E |
8 |
5 |
1000 |
1600 |
200 |
0 |
||
TOTAL COST |
3600 |
350 |
MIN COST OF CRASHING BY 4 PERIODS = 350