Question

Perform a cost-benefit analysis using the following data: Direct Costs • Ten laptops—$2,000/each • A server—$2,000...

Perform a cost-benefit analysis using the following data:

Direct Costs

• Ten laptops—$2,000/each

• A server—$2,000 •

Network installation—$15,000 •

Software—$20,000

Indirect Costs

• Training—$15,000

Annualized Benefits

• Increased capacity—$100,000

Homework Answers

Answer #1

Total Direct Cost = ( 10 x 2000) + 2000 + 15000 + 20000 = $ 57000

Total Indirect Cost = $ 15000

Total Cost = Total Direct Cost + Total Indirect Cost = 57000 + 15000 = $ 72,000

Annualized Benefit = $ 100,000

Payback Period( in years) = Total Cost / Annualized Benefit = 72,000 / 100,000 = 0.72 years

Payback Period (in days) = 0.72 x 365 = 262.8 = 263 days (Rounding off)

Therefore, the payback period is less than a year.

The total cost is less than the Annualized benefit resulting in a payback period of less than a year, hence it is a good cost-benefit scenario.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Perform a benefit /cost (B/C) analysis the for the following direct benefit projects having the same...
Perform a benefit /cost (B/C) analysis the for the following direct benefit projects having the same life time of 6 years and interest rate of 9% by finding the difference in B/C (i.e. incremental B/C) to select only one project. Write in the answer box the final result of the incremental B/C analysis. The projects have the following details, all calculated in AW form: Project A : benefits = $102,817, cost =$70,849 and disbenefits =$5,208 Project B : benefits =...
Perform a cost benefit analysis for the following scenario. the email server in your company has...
Perform a cost benefit analysis for the following scenario. the email server in your company has an estimated value of $5000000. s sabotage or vandalism scenario indicated that 17 percent of the web site would be damaged or destroyeed oin such an attack. an attack of this type can occure twice a year . the comapny had invested in a risk control solution and managed to bring the attack frequency to once every two year, the annual cost of control...
Perform a benefit /cost analysis for the following usage cost projects having the same life time...
Perform a benefit /cost analysis for the following usage cost projects having the same life time of 5 years and interest rate of 2% by finding the incremental benefits/costs in steps one after the other. You have to write only the final value of incremental benefits/costs in the required answer field. The three projects have the following values, all calculated in PW form: Project 1 : benefits = $51,138 and cost =$14,831 Project 2 : benefits = $79,480 and cost...
Perform a financial analysis for a project where you will show costs, discount factor for cost,...
Perform a financial analysis for a project where you will show costs, discount factor for cost, and discounted costs as well as benefit, discount factor for benefit and discounted benefit for each year starting from year 0. Assume the projected cost and benefits for this project are spread over four years as follows: Estimated costs are $145,000 in year 0 and $45,000 each year in years 1, 2, and 3, and estimated benefits are $0 in year 0 and $210,000...
9) Antuan Company set the following standard costs for one unit of its product. Direct materials...
9) Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $4.00 per Ib.) $ 16.00 Direct labor (1.7 hrs. @ $13.00 per hr.) 22.10 Overhead (1.7 hrs. @ $18.50 per hr.) 31.45 Total standard cost $ 69.55 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per...
Antuan Company set the following standard costs for one unit of its product. Direct materials (3.0...
Antuan Company set the following standard costs for one unit of its product. Direct materials (3.0 Ibs. @ $5.00 per Ib.) $ 15.00 Direct labor (2.0 hrs. @ $11.00 per hr.) 22.00 Overhead (2.0 hrs. @ $18.50 per hr.) 37.00 Total standard cost $ 74.00 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...
Apply the high-low method of cost analysis to the three cost data groups shown below. Volume...
Apply the high-low method of cost analysis to the three cost data groups shown below. Volume (applicable to each group) Group A Costs Group B Costs Group C Costs 2,000 $3,900 $1,500 $3,600 12,000 18,900 9,000 3,600 16,000 24,900 12,000 3,600 20,000 30,900 15,000 3,600 What cost behavior patterns are apparent? Express each as a cost formula: Total cost = Fixed costs + (Variable cost x Volume). Group Fixed costs + (Variable cost x Volume) A Answer + Answer x...
r Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Road Gripper Tire Co. manufactures...
r Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Road Gripper Tire Co. manufactures automobile tires. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 4,160 tires were as follows: Standard Costs Actual Costs Direct materials 100,000 lbs. at $6.40 101,000 lbs. at $6.50 Direct labor 2,080 hrs. at $15.75 2,000 hrs. at $15.40 Factory overhead Rates per direct labor hr., based on 100% of normal capacity of 2,000...
1- Determine what type of costs for each statement. Variable Cost , Sunk Cost , Direct...
1- Determine what type of costs for each statement. Variable Cost , Sunk Cost , Direct Cost , Life Cycle Cost , Opportunity Cost , Indirect Cost , Fixed Cost a- The costs associated with running the business, e.g. management salaries, rent, insurance? b- A previously incurred cost that has no bearing on future decisions is also known as a? c- The benefit you forego by selecting one alternative over another. d- Costs that change with the amount of units...
You are in charge of an EHR implementation project at your clinic. Before the project can...
You are in charge of an EHR implementation project at your clinic. Before the project can proceed, your upper management has asked you to put together an ROI analysis on the costs and benefits of the EHR implementation project. Your management is requiring that you include cost benefit analysis for the next five years. EHR implementation takes place in 2015 and benefits from the implementation are assumed to begin right away in 2015. The ROI analysis should include years 2015...