1- Find the optimal load size from the following cases for two machines if the processing time is 1 time unit per piece and material handling time is 2 time unit per move. Use Excel to solve the problem and draw the chart for Completion time Vs Unit load size
a) Unit load size is 14 pieces and number of transfers is 1
b) Unit load size is 7 pieces and number of transfers is 2
c) Unit load size is 2 pieces and number of transfers is 7
d) Unit load size is 1 pieces and number of transfers is 14 (b) What is the effect of unit load size on job completion times?
Material handling Time (Transfer time/Load time )
Answer-
Given values-
Preparing time (handling time) : 1 time unit/piece
Material taking care of Time (Transfer time/Load time ): 2 time unit/piece/move
Section a) case 1 => 14 (2) + 1(1) = 29 time units
case 2 => 7 (2) + 2(1) = 16 time units
case 3 => (2) + 7(1) = 11 time units
case 4 => 1 (2) + 14(1) = 15 time units
So the ideal burden esteem is case 3.
Part B) answer -
Lower the unit load size , prior the activity fulfillment time.
Please like my answer.