Question

The process where we shorten the duration of a project in the cheapest manner possible. a....

The process where we shorten the duration of a project in the cheapest manner possible.

a. Project minimization

b. Project crashing

c. Project leaking

d. Project alignment

Homework Answers

Answer #1

The process where we shorten the duration of a project in the cheapest manner possible.is known as project crashing.

Project Crashing is the process of reducing the project duration by decreasing the time of one or more than one critical activity in the project. It restricts project activity to lesser time than normally required. The shortening of the time from normal activity is often called crashing. This can be achieved by assigning more resources, measured monetarily (usually in dollars) to the activities which are to be crashed.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
in PERT, the probability of completing the project at the project expected duration is: A. 100%...
in PERT, the probability of completing the project at the project expected duration is: A. 100% B. 70% C. 50% D. Less than 25% E. Less than 40% and why?
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is...
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is $525,000. The project is in its 25th week. The actual cost (thus far) is $270,000. At this point in the plan, the planned cost was expected to be $261,000. For the work performed to date, the earned value is estimated at $272,000. Compute the following for the project (10 points) a) Cost variance. b) Schedule variance. c) If rest of the project is assumed...
We want to explore a possible connection between the variables x and /, where x =...
We want to explore a possible connection between the variables x and /, where x = number of days and words spoken and y = price of MB. a) So far we have the followirtg, f = 12.77x+ b, f = 38.5, Y = 1925, find b. b) Consider the regression equation of y on x given by: y = 116.9 x + 115.725 along with I* = 24.6, x = 2,46, s" = 3.77 and n = 10. Construct....
Swimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists...
Swimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before Memorial Day weekend (pool opening weekend). You would like to find the minimum cost schedule for your project. There is a $9,000 per week penalty for each week the project is delayed beyond week 9. In addition, your project team determined that indirect costs are $15,000 per week. ACTIVITY Immediate Predecessor (s)...
Define Scope is the process of developing the: ​ a. project scope management plan. b. project...
Define Scope is the process of developing the: ​ a. project scope management plan. b. project scope network diagram. c. detailed specifications of the project outcomes and products. d. project work breakdown structure.
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent...
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent Completed A 3.00 - 15000 1.00 B 1.00 A 5000 0.00 C 2.00 A 10000 1.00 D 3.00 A 21000 0.50 E 2.00 B,C 32000 0.00 F 1.00 C 5000 0.00 G 1.00 C 5500 0.00 The project started on June 1st. The project has a planned duration of 7 months. Data below are planned cost and actual cost (spent) from June to November:...
Question 03. Using the information in the table below, assuming that the project team will work...
Question 03. Using the information in the table below, assuming that the project team will work a standard working week (5 working days in a week) and that all tasks will start as soon as possible: Task Description Duration (Working days) Predecessor/s A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D telecoms 15 B E Hardware installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training/Support 5 G I...
The R&D Department is planning to bid on a large project for the development of a...
The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes.  The accompanying table shows the activities, times, and sequences required: Activity Immediate Predecessor Optimistic Most Likely Pessimistic A - 3 6 8 B A 2 4 4 C A 1 2 3 D C 6 7 8 E B,D 2 4 6 F B 6 10 14 G E, F 1 2 4 H F 3 6 9 I...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...