Which of the following questions does a project manager NOT have to address when considering resources allocated to a project?
Multiple Choice
Will the assigned labor be adequate and available to deal with my project?
Will outside contractors have to be used?
Will scope have to be redefined/stabilized?
Do unforeseen resource dependencies exist?
How much flexibility do we have in using resources?
Ans - Will scope have to be redefined/stabilized?
When the resource are assigned, project manager needs to know:
· Whether the assigned resources are adequate to do the task?
· Are there requirement of external resources like contractor in case resources are not sufficient?
· Are there unforeseen resource dependencies so that it can be tackled and managed upfront?
· How much is flexibility in using resources so that it can be put to maximum use?
· Basis the resources assigned, are there any challenges in meeting the timeline?