The following table lists the components needed to assemble an
end item, lead times (in weeks), and quantities on hand.
Item lead time Amount on Hand Direct Components
End 3 0 L(2), C(1), K(3)
L 3 12 B(2), J(3)
C 4 15 G(2), B(2)
K 4 21 H(4), B(2)
B 3 32
J 4 27
G 4 5
H 3 0
a. If 43 units of the end item are to be assembled, how many
additional units of B are needed? (Hint: You don’t need to develop
an MRP plan.)
An order for the end item is scheduled to be shipped at the
start of week 17. What is the latest week that the order can be
started and still be ready to
ship on time? (Hint: You don’t need to develop an MRP plan.)
Item | LT | OH | Components |
End | 3 | 0 | L(2), C(1), K(3) |
L | 3 | 12 | B(2), J(3) |
C | 4 | 15 | G(2), B(2) |
K | 4 | 21 | H(4), B(2) |
B | 3 | 32 | |
J | 4 | 27 | |
G | 4 | 5 | |
H | 3 | 0 |
(a)
43 units of End item require 86 L, 46 C, ad 129 K on a gross basis.
Net requirement of L = 86 - 12 = 74
Net requirement of C = 46 - 15 = 31
Net requirement of K = 129 - 21 = 108
Gross requirement of B = 74 x 2 + 31 x 2 + 108 x 2 = 426
Net requirement of B = 426 - 32 = 394
(b)
So, the order must be started latest by week 6 beginning in order to finish the end item by week 17 beginning.