The following table lists the components needed to assemble an end item, lead times (in weeks),...

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.

Item lead time Amount on Hand Direct Components
End 3 0 L(2), C(1), K(3)
L 3 12 B(2), J(3)
C 4 15 G(2), B(2)
K 4 21 H(4), B(2)
B 3 32
J 4 27
G 4 5
H 3 0
a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)

An order for the end item is scheduled to be shipped at the start of week 17. What is the latest week that the order can be started and still be ready to
ship on time? (Hint: You don’t need to develop an MRP plan.)

Homework Answers

Answer #1
Item LT OH Components
End 3 0 L(2), C(1), K(3)
L 3 12 B(2), J(3)
C 4 15 G(2), B(2)
K 4 21 H(4), B(2)
B 3 32
J 4 27
G 4 5
H 3 0

(a)

43 units of End item require 86 L, 46 C, ad 129 K on a gross basis.

Net requirement of L = 86 - 12 = 74
Net requirement of C = 46 - 15 = 31
Net requirement of K = 129 - 21 = 108

Gross requirement of B = 74 x 2 + 31 x 2 + 108 x 2 = 426

Net requirement of B = 426 - 32 = 394

(b)

So, the order must be started latest by week 6 beginning in order to finish the end item by week 17 beginning.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Problem 12-3 The following table lists the components needed to assemble an end item, lead times...
Problem 12-3 The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
Problem 5 Eighty units of end item E are needed at the beginning of week 6....
Problem 5 Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 20 units of J now on hand. Lead times...
The following table lists the components used in assembling item FG-A. The following information is also...
The following table lists the components used in assembling item FG-A. The following information is also included for each component: lead time, the on-hand supply, and direct components. Item Lead Time (days) Available Inventory Direct Components FG-A 1 0 SA-B(1), SA-C (2), SA-D(2) SA-B 1 0 SA-D(2) SA-C 2 0 E (1), F(2) SA-D 2 0 E(3) E 1 10 --- F 3 5 --- Construct a product structure tree at a lowest level coding. Prepare a time-phased product structure....
An end item’s demand forecasts for the next 10 weeks are 30, 20, 35, 50, 25,...
An end item’s demand forecasts for the next 10 weeks are 30, 20, 35, 50, 25, 25, 0, 40, 0, and 50 units. The current on-hand inventory is 80 units. The order policy is to produce in lots of 100. The booked customer orders for the item, starting with week 1, are 22, 30, 15, 9, 0, 0, 5, 3, 7, and 0 units. At present, no MPS quantities are on-hand for this item. The lead time is 2 weeks....
Product A is made from components B and C. Item​ B, in​ turn, is made from...
Product A is made from components B and C. Item​ B, in​ turn, is made from D and E. Item C also is an intermediate​ item, made from F and H.​ Finally, intermediate item E is made from H and G. Note that item H has two parents. The following are item lead​ times: Item A B C D E F G H Lead Time​ (weeks) 1 1 2 2 6 4 4 6 a. What lead time​ (in weeks)...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 10 15 45 10 30 90 20 45 160 Use the least total cost lot-sizing method to determine the quantity to order with...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 85 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 55 10 22 70 87 19 63 210 58 Use the least total cost and the least unit cost lot-sizing methods to determine...
Product A is assembled from 6 components. The components are B, C, D, E, F, G....
Product A is assembled from 6 components. The components are B, C, D, E, F, G. Components B, D, and F are purchased from a supplier, complete and ready to assemble. Component C is assembled from parts H, I, and J. Component E is assembled from parts K and L. Component G is made in the plant from raw materials. Part H is made from parts M and N. Part L is made from parts P, Q, and R. Part...
Product Y is made from one component P, three components Q, and one 2 components R.  P...
Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes: Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock Y                         1                                 lot-for-lot               30                                              none                                          5 P                        2                                   40                              15                                              none                                          none Q                        2                                 100                               8                                               none                                          8 R                        3                                 120                             30                                              none                                          none S                         2                                 500                             20                                              500, week 1                          20 T                         2                                 600                           370                                             none                                          50 a.    Draw the BOM for product Y. b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions Master Production Schedule Finished...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT