Question

PERT Consider the following table: Activity Prec. Act t0 tml tp te A - 3 4...

PERT

Consider the following table:

Activity Prec. Act t0 tml tp te
A - 3 4 5 4
B - 5 8 11 8
C A 1 2 3 2
D B 2 5 8 5
E B 4 6 8 6
F C,D 1 1 1 1
G E 3 4 5 4
H G,F 2 3 4 3

1) Construct a PERT network.

[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]

2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.

3) Find the completion time and the standard deviation (σ) for the project— round off the standard deviation to the nearest hundredth: two decimal places.  

4) What is the completion time at 95% and 99% confidence levels?

5) What is the likelihood of this project being completed earlier than 20 days?

5) Between 21 and 23 days?

Homework Answers

Answer #1
Task O M P Te Var^0.5 Variance
A 3 4 5 4 0.333333 0.111111
B 5 8 11 8 1 1
C 1 2 3 2 0.333333 0.111111
D 2 5 8 5 1 1
E 4 6 8 6 0.666667 0.444444
F 1 1 1 1 0 0
G 3 4 5 4 0.333333 0.111111
H 2 3 4 3 0.333333 0.111111

Activity ES EF LS LF SLACK
A 0 4 11 15 11
B 0 8 0 8 0
C 4 6 15 17 11
D 8 13 12 17 4
E 8 14 8 14 0
F 13 14 17 21 4
G 14 18 14 18 0
H 18 21 18 21 0

Critical path is BEGH with duration 21

Variance of critical path =1.6666

SD of critical path = (1.6666)^0.5 =1.29

Completion time at 95% confidence i given by

z = T-Mean/SD = T- 21/1.29

1.645 = T-21/1.29

T=22.665

Completion time at 99% confidence is given by

2.33 = T-21/1.29

T = 24

Note: As per policies, I can answer first 4 parts of a question. Inconvenience is regretted.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)      &nbsp
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)          to           tml                tp                                 te     A                     -----                        1                      2                      3                           B                      A                           2                      4                      6     C                      B                            1                      4                      7     D                      B                            3                      4                      5     E                      C                            1                      3                      5     F                      D, E                       2                      3                      4 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.] 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time and the standard deviation (σ) for the project— round off the standard deviation to the nearest...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What is the slack of activity B? 8 0 3 2 7
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. CAN ONLY BE ONE OF THE OPTIONS it's not 5 I tried that. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What...
Path Activity to tm tp te=(to+4tm+tp)/6 Path total A-C-F-H A 3 4 5 4 19 C...
Path Activity to tm tp te=(to+4tm+tp)/6 Path total A-C-F-H A 3 4 5 4 19 C 2 3 10 4 F 3 5 7 5 H 2 6 10 6 B-D-F-H B 5 7 9 7 23 D 2 5 8 5 F 3 5 7 5 H 2 6 10 6 B-E-G B 5 7 9 7 21 E 1 7 7 6 G 7 8 9 8 The critical path is B-D-F-H. Hence, the expected duration of project...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT