Question

(6) The ?nal step to putting together the project plan is to assign the resources. Good...

(6) The ?nal step to putting together the project plan is to assign the resources. Good project management is about the maximizing of resources against the project plan. The effective and efficient use of resources helps ensure a project is on time, within budget, and meets scope. Three strategies/approaches are usually considered when leveling resources.

List and explain each of the three strategies (10 Points).

Homework Answers

Answer #1

Resource levelling means the effective utilisation of the available resources of a project which makes the project get completed on time, cost of the project will also be within the budget. Resource levelling can be done using any of the 3 strategies which are

1. utilisation of slack

2.rescheduling the finish date

3. smoothing

1. For every project we have some slack time which is the possible time for delay which can be tolerated. We can use this time to push some activities to that so that the resources can be used as per plan . This helps in levelling the resources .

2. We can push off the finish date so that the time gets increased and work gets done in a calm manner which helps in effective utilisation of the available resources which helps in resource levelling.

3. Smoothing is setting limits for the utilisation of resources at every step of the project and this makes us to utilise only resources planned for that step. This helps us in levelling the reosurces which we already planned and segregated as per the requirement.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Not so much a question but I was wondering what would be a list of 2-3...
Not so much a question but I was wondering what would be a list of 2-3 questions to ask after reading this case analysis that would be good to ask. Meaning, after reading this case analysis what questions would you want to ask for the writer? Thanks, Alex - Industry Scenario The tech industry is highly volatile at the point of time with people changing jobs every eighteen months on average. Compensation is getting higher and people are becoming tough...
SECTION A: CASE TWO READ THE CASE CAREFULLY AND ANSWER THE QUESTIONS THAT FOLLOW DIGITAL SERVICE...
SECTION A: CASE TWO READ THE CASE CAREFULLY AND ANSWER THE QUESTIONS THAT FOLLOW DIGITAL SERVICE FOR STUDENTS IN HIGHER EDUCATION (DSSHED) Digital Service for Students in Higher Education (DSSHED) is an innovation platform for the creators of next generation products and services. It was founded by the Ingenious Investment Group (IIG). The objective of DSSHED is to boost multidisciplinary agile innovation culture and encourage entrepreneurship in its catchment region. DSSHED provides students and companies with a collaborative and multidisciplinary...
1.Establishing the virtual Management: As known, managing virtual staff requires a different method or approach than...
1.Establishing the virtual Management: As known, managing virtual staff requires a different method or approach than managing local staff. Due to that reason, Golden Scent has developed a strategic plan to successfully manage its virtual staff in the USA. Identify the suitable manager. to make sure our work will proceed as we planned, Golden Scent willrecruit a virtual manager with the essential skills and knowledge required to manage virtual employees. Find the skilled people to work with. Since not everyone...
The Business Case for Agility “The battle is not always to the strongest, nor the race...
The Business Case for Agility “The battle is not always to the strongest, nor the race to the swiftest, but that’s the way to bet ’em!”  —C. Morgan Cofer In This Chapter This chapter discusses the business case for Agility, presenting six benefits for teams and the enterprise. It also describes a financial model that shows why incremental development works. Takeaways Agility is not just about the team. There are product-management, project-management, and technical issues beyond the team’s control. Lean-Agile provides...
CASE 3.2 Horizon Consulting Patti Smith looked up at the bright blue Carolina sky before she...
CASE 3.2 Horizon Consulting Patti Smith looked up at the bright blue Carolina sky before she entered the offices of Horizon Consulting. Today was Friday, which meant she needed to prepare for the weekly status report meeting. Horizon Consulting is a custom software development company that offers fully integrated mobile application services for iPhonetm, Androidtm, Windows Mobile® and BlackBerry® platforms. Horizon was founded by James Thrasher, a former marketing executive, who quickly saw the potential for digital marketing via smartphones....
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation....
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation. case:    W17400 APIGEE: PEOPLE MANAGEMENT PRACTICES AND THE CHALLENGE OF GROWTH Ranjeet Nambudiri, S. Ramnarayan, and Catherine Xavier wrote this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be...
Please answer this question in short essay form (2-4 paragraphs) Considering that cultures as complicated and...
Please answer this question in short essay form (2-4 paragraphs) Considering that cultures as complicated and socially constructed through the communicative interaction of organizational members. Briefly describe how the organizational concepts of complicated, emergent, unitary, and ambiguous apply to the sample auto-ethnography. Sample Auto-ethnography: Required Reading Auto-ethnography of College X Joe Student Organizational Culture and Diversity 223-58000 “The organization’s culture has both a direct and an indirect impact on the allocation of power among diverse groups. The values and ideologies...