Dell uses the CR5 chip in some of its laptop computers. The prices for the chip during the past 6 months were as follows: Month Actual
Price per Chip
1 1.90
2 1.65
3 1.70
4 1.85
5 1.90
6 1.87
a. Use a 2-month moving average to forecast demand from month 4 to month 6
b. Use a 3-month moving average to forecast demand from month 4 to month 6.
c. Which forecasting is better (Using the mean absolute deviation): the 2- month average or the 3-month average?
units |
Price |
2 month moving average |
2 months moving average |
Absolute Deviation |
3 month moving average |
3 month moving average |
Deviatiom |
1 |
1.9 |
||||||
2 |
1.65 |
||||||
3 |
1.7 |
||||||
4 |
1.85 |
(1.65+1.7)/2 |
1.675 |
0.175 |
(1.9+1.65+1.7)/3 |
1.750 |
0.100 |
5 |
1.9 |
(1.7+1.85)/2 |
1.775 |
0.125 |
(1.65+1.7+1.85)/3 |
1.733 |
0.167 |
6 |
1.87 |
(1.85+1.9)/2 |
1.875 |
0.005 |
(1.7+1.85+1.9)/3 |
1.817 |
0.053 |
Sum |
0.305 |
0.32 |
|||||
MAD = Sum(A-F)/n |
|||||||
For 2 month moving average = 0.305/3=0.102 |
|||||||
For 3 month moving average = 0.32/3=0.107 |
|||||||
As MAD is slightly higher for 3 months moving average, so the accurate method will be the 2-month moving average method. |