Question

A project activity has an optimistic time estimate of three days, a most likely time estimate...

A project activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:

7

7.5

8

8.5

10

Homework Answers

Answer #1

Answer: 7.5

Explanation:

Given optimistic time estimate, o = 3 days

Most likely time estimate, m = 8 days

Pessimistic time estimate, p = 10 days

Expected time for the activity, Te = [o + 4m + p]/6

                                             = [3+ (4 x 8) + 10] / 6 = 7.5 days

Hence the answer is second option, 7.5

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most...
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most likely (ML), and pessimistic(PS) estimates are given. If the interest rate is 20%, what is the expected NPV? Parameter Pessimistic Most Likely Optimistic Fist cost 150000 100000 80000 Annual benefit 25000 45000 50000 Project life 5 7 9
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most...
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most likely (ML), and pessimistic(PS) estimates are given. If the interest rate is 20%, what is the expected NPV? Parameter Pessimistic Most Likely Optimistic Fist cost 150000 100000 80000 Annual benefit 25000 45000 50000 Project life 5 7 9
Use the following activities and their three duration estimates (in days) to do the following Determine...
Use the following activities and their three duration estimates (in days) to do the following Determine the expected duration of the project – use 2 decimals when determining the duratio Path Activity Optimistic Most Likely Pessimistic a-b-c A 4 5 6 B 7 8 10 C 3 5 9 d-e-f D 7 8 11 E 2 3 4 f 1 4 6
A project has the following tasks and duration estimates given. These three tasks are done in...
A project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation...
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
Use the table below to answer the questions Activity Optimistic duration Pessimistic duration Most Likely duration...
Use the table below to answer the questions Activity Optimistic duration Pessimistic duration Most Likely duration Weighted duration Immediate Predecessor P 15 27 21 - Q 18 36 24 P R 26 40 24 P S 21 39 27 Q T 27 33 24 Q,R U 16 32 24 S,T V 16 30 26 U 1. Calculate the actual duration of each activity (fill-in the table) 2. Draw an AOA network diagram for the activities (in the space below): 3....
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...