Question

In “crashing” a project, a manager will generally focus on activities which: are NOT on the...

In “crashing” a project, a manager will generally focus on activities which:

are NOT on the critical path

are the least costly to crash

are costly to crash and are on the critical path

are on the critical path and are the least costly to crash

are the easiest to crash

Homework Answers

Answer #1

Crashing of a project is done to reduce duration of a project.

A project will have multiple paths of activities. One of these paths with longest duration is called critical path and others are called non critical path,

If a project needs to be crashed . i.e. its duration needs to be reduced, the critical activity needs to be crashed first

Having chosen the critical path, the manager will focus on crashing the activity which has least cost of crashing .

Therefore , answer would be “ are on the critical path and are the least costly to crash”

ANSWER : ARE ON THE CRITICAL PATH AND ARE THE LEAST COSTLY TO CRASH

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
13. In critical path management, which is a general rule for crashing activities? A. Crash activities...
13. In critical path management, which is a general rule for crashing activities? A. Crash activities on the critical path B. Crash activities that are not on the critical path C. Crash activities having the greatest number of predecessor activities D. Crash activities having the greatest number of following activities E. Crash activities having the lowest crashing costs 14. Suppose a project has a crash time of 40 weeks. The normal cost of the project is $60,000, and the crash...
When attempting to crash a project to reduce its overall duration, the only logical candidate tasks...
When attempting to crash a project to reduce its overall duration, the only logical candidate tasks for crashing are those on the critical path. Why is this
Question: The project’s progress has fallen behind schedule on the critical path. The project manager has...
Question: The project’s progress has fallen behind schedule on the critical path. The project manager has decided to recover the schedule by crashing the project’s schedule. What is the expected consequence of this project’s triple constraints?
A project with nine activities includes only four paths that are shown below along with their...
A project with nine activities includes only four paths that are shown below along with their lengths. The following table provides the opportunities for crashing activities. Activity Maximum Reduction Crash Cost/Day A 2 $900 B - - C - - D 2 $200 E 2 $400 F 2 $700 G 1 $500 H - - I 2 $800 Suppose each day of shortening (crashing) the project saves $1200. Determine how many days should the project be crashed, and report the...
What is the term used for shortening a logic network after construction has begun? Crashing Fast...
What is the term used for shortening a logic network after construction has begun? Crashing Fast tracking Resource leveling Time-scaled network How is free-float defined? The amount of slack between activities The amount of slack within a path of activities The amount of slack accumulated throughout the logic network The amount of slack in a node The path with the longest sequence of activities in a project plan is called: Crises Critical Concrete Detailed        Lead-times are used to determine...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above Reset Selection Question 9 of 21 Which of the following is NOT included in project control? A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. All of the above are included Reset Selection Question 10 of 21...
Below are the project steps for the creation of a television advertisement for Foolio, which is...
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created.    Consider the following data for questions 1 through 5: Activity Duration (days) Description Preceding Activity(ies) A 6 Create script for advertisement - B 4 Book technical crew A C 4 Book actors A D 3 Create props and costumes B,C E 6 Book location C F 5 Filming and editing D,E How many paths...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
A project manager, in preparation for the construction of roads, has identified the activities and their...
A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table). Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D J 3 F K 8 E,H L 4 C,J (a) How long the project will take? (b) State the critical activities. (c)...
The information for project X is shown below. What are the critical path and the completion...
The information for project X is shown below. What are the critical path and the completion time of the project? Crashing Costs Activity Preceding Normal Time 1st Week 2nd Week K — 8 weeks $4100 — L K 6 weeks 3250 — N K 1 week 450 450 M L 5 weeks 3000 3500 J N 4 weeks 500 — Q J,M 6 weeks 4000 4000 KLMQ, 25 weeks KLNMJQ: 25 weeks KNJQ, 25 weeks KNJQ, 30 weeks KLMQ, 30...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT