In “crashing” a project, a manager will generally focus on activities which:
are NOT on the critical path |
||
are the least costly to crash |
||
are costly to crash and are on the critical path |
||
are on the critical path and are the least costly to crash |
||
are the easiest to crash |
Crashing of a project is done to reduce duration of a project.
A project will have multiple paths of activities. One of these paths with longest duration is called critical path and others are called non critical path,
If a project needs to be crashed . i.e. its duration needs to be reduced, the critical activity needs to be crashed first
Having chosen the critical path, the manager will focus on crashing the activity which has least cost of crashing .
Therefore , answer would be “ are on the critical path and are the least costly to crash”
ANSWER : ARE ON THE CRITICAL PATH AND ARE THE LEAST COSTLY TO CRASH |