Question

Given is a CPM project network diagram as shown below. Activity Start A B C D...

Given is a CPM project network diagram as shown below.

Activity

Start

A

B

C

D

E

F

G

H

End

days

0

2

6

8

3

4

2

3

2

0


a) The Project Completion time = ____ days.

b) The Earliest Start time, ES, of Activity G = ____ days.

c) The Latest Finish time, LF, of Acitivity C = ____ days.

d) The critical activities are = ____ (ex. Fill in answer as: ABCD)

Homework Answers

Answer #1

a) Solution for Project Completion time

Path & Duration are:

ACFH = 5+9+8+4 = 26

ACEGH = 5+9+9+5+4 = 32

BDGH = 6+6+5+4 = 21

Project completion time will be maximum of path duration = 32days

ES, the earliest time activity can start, assuming all preceding activities start as early as possible.

EF, the earliest time the activity can finish.

LS, the latest time the activity can start and not delay the project.

LF, the latest time the activity can finish and not delay the project

Computation of earliest starting and finishing times is aided by two simple rules:

1. The earliest finish time for any activity is equal to its earliest start time plus it's expected duration, t:

EF = ES + t

2. ES for activities at nodes with one entering arrow is equal to EF of the entering arrow. ES for activities leaving nodes with multiple entering arrows is equal to the largest EF of the entering arrow.

Computation of the latest starting and finishing times is aided by the use of two rules:

1. The latest starting time for each activity is equal to its latest finishing time minus its expected duration:

LS = LF - t

2. For nodes with one leaving arrow, LF for arrows entering that node equals the LS of the leaving arrow. For nodes with multiple leaving arrows, LF for arrows entering that node equals the smallest LS of leaving arrows.

and therefore;

b) ES of G = 23days

c) LF of C = 14days

d) Critical activities are those in the critical path, ACEGH

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
1. Given is a PERT project network diagram as shown below: Activity Start A B C...
1. Given is a PERT project network diagram as shown below: Activity Start A B C D E F G H I J K End Time 0 18 24 21 38 28 34 22 20 34 34 16 0    a) The Project Completion time =   b) The Earliest Start time, ES, of Activity F =   c) The Earliest Start time, ES, of Activity K =   d) The Latest Start time, LS, of Activity E =   e) The non-critical activities...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times: Immediate Activity Predecessor Time A — 3 B — 4 C — 2 D A, B, C 2 E A, D 8 F C, D 7 G D, E 5 H F...
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
Assume that activity F has the following times: Early start time (ES) = 7 days Early...
Assume that activity F has the following times: Early start time (ES) = 7 days Early finish time (EF) = 13 days Latest start time (LS) = 15 days Latest finish time (LF) = 21 days Which of the following statements is TRUE about activity F? Activity F takes 14 days to complete Activity F is on the critical path Activity F has 8 days of slack time Activity F is the first activity of the project None of the...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There can be multiple critical paths on the same project, all with different durations. B) The early finish of an activity is the latest early start of all preceding activities. C) The late start of an activity is its late finish plus its duration. D) If a specific project has multiple critical paths, all of them will not have the same duration. E) B) and...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT