EV= 30,000 , PV= 40,000 , AC= 45,000 , CPI= 0.667 , SPI= 0.75
Budgeted value= 50,000
Calculate the following:
1. Using the above EV, AC, and BAC to calculate the estimate at completion value for estimated to complete work performed at the budgeted rate.
EAC =
2. Using the above EV, AC, BAC, and CPI calculate the estimate at completion value for estimated to complete work performed at the present CPI.
EAC =
3. Using the above EV, AC, BAC, CPI, and SPI to calculate the estimate at completion value for estimated to complete work considering both SPI and CPI factors:
EAC =
4. Using the above EV, AC, BAC, and EAC (for problem 1, calculate To Complete Performance Index (based on the EAC.))
TCPI =
Question – 1:
EAC = BAC/CPI = BAC/(EV/AC) = 50000/(30000/45000) = 50000/0.667 = 75000
Question – 2:
EAC = BAC/CPI = 50000/0.667 = 75000
Question – 3:
EAC = AC + [(BAC – EV)/(CPI*SPI)]
= 45000 + [(50000 – 30000)/(0.667*0.75)
= 45000 + 20000/ 0.50
= 45000 + 40000
= 85000
Question – 4:
TCPI = (BAC – PV)/(EAC – AC)
= (50000 – 40000)/(75000 – 45000)
= 10000/30000
= 1/3 = 0.33
********
IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!
IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!
Get Answers For Free
Most questions answered within 1 hours.