Question

EV= 30,000 , PV= 40,000 , AC= 45,000 , CPI= 0.667 , SPI= 0.75 Budgeted value=...

EV= 30,000 , PV= 40,000 , AC= 45,000 , CPI= 0.667 , SPI= 0.75

Budgeted value= 50,000

Calculate the following:

1. Using the above EV, AC, and BAC to calculate the estimate at completion value for estimated to complete work performed at the budgeted rate.

EAC =

2. Using the above EV, AC, BAC, and CPI calculate the estimate at completion value for estimated to complete work performed at the present CPI.

EAC =

3. Using the above EV, AC, BAC, CPI, and SPI to calculate the estimate at completion value for estimated to complete work considering both SPI and CPI factors:

EAC =

4. Using the above EV, AC, BAC, and EAC (for problem 1, calculate To Complete Performance Index (based on the EAC.))

TCPI =

Homework Answers

Answer #1

Question – 1:

EAC = BAC/CPI = BAC/(EV/AC) = 50000/(30000/45000) = 50000/0.667 = 75000

Question – 2:

EAC = BAC/CPI = 50000/0.667 = 75000

Question – 3:

EAC = AC + [(BAC – EV)/(CPI*SPI)]

= 45000 + [(50000 – 30000)/(0.667*0.75)

= 45000 + 20000/ 0.50

= 45000 + 40000

= 85000

Question – 4:

TCPI = (BAC – PV)/(EAC – AC)

= (50000 – 40000)/(75000 – 45000)

= 10000/30000

= 1/3 = 0.33

********

IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!

IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Please read the article and answear about questions. Determining the Value of the Business After you...
Please read the article and answear about questions. Determining the Value of the Business After you have completed a thorough and exacting investigation, you need to analyze all the infor- mation you have gathered. This is the time to consult with your business, financial, and legal advis- ers to arrive at an estimate of the value of the business. Outside advisers are impartial and are more likely to see the bad things about the business than are you. You should...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT