1) All of the following are reasons for project teams to be made up of members who perform project roles except:
A - Project roles promote division of labor
B - Project roles funnel the right attention to all project areas
C - Project roles create an opportunity for the organization to train new project managers
D - Project roles concentrate expertise within specific roles
2) . All of the following are part of a project methodology except:
A - Allowing stakeholders to change the methodology to add scope to the project
B - What to do in case of exceptions in any step of the methodology
C - Who is accountable for a particular step in the methodology
D - Exit criteria for a step in a methodology
Question:- All of the following are reasons for project teams to be made up of members who perform project roles except:
Answer:- C - Project roles create an opportunity for the organization to train new project managers
Reason:- Project roles are more focused on having the different activities of the product to be divided among the team members for ensuring the timely completion of the project within specified budget
Question:- 2) . All of the following are part of a project methodology except:
Answer:- A - Allowing stakeholders to change the methodology to add scope to the project
Reason:-
Project methodology is mainly used to explain the five different process of project management namely define, plan, launch, manage, and close and it does not allow any kind of change in the methodology