Question

Two retailers are considering inventory management of one of the products they are both selling. Each...

Two retailers are considering inventory management of one of the products they are both selling. Each of them has an average demand of 12 units per week with a standard deviation of 2 units per week. The supply lead time is constant and equal to 2 weeks.

1. How much safety stock should each retailer keep to achieve a service level of 95% (z = 1.64)? Imagine now that those two retailers are going to be combined into one integrated retailer, which will be facing the combined demand of the previous two retailers.

2. What is the average and the standard deviation of the integrated weekly demand?

3. How much safety stock should the integrated retailer keep to achieve the same service level of 95% (z = 1.64)?

4. What is the impact of integration on the total safety stock level? What if 30 stores where integrated? (Hint: Compare the safety stock of the integrated retailer with the combined safety stocks of the two previous retailers and conclude.)

Homework Answers

Answer #1

Answer to question 1 :

Safety stock = Z value x Standard deviation of weekly demand x Square root ( Lead time ) = 1.64 x 2 x Square root ( 2 ) = 1.64x2x1.414= 4.637

Answer to question 2 :

Average demand when two retailers are combined = ( average demand of retailer 1 + average demand of retailer 2) /2 = ( 12 + 12) /2 = `12

Variance when two retailer’s demand are combined = Variance of demand of retailer 1 + Variance of demand of retailer 2 = 2^2 + 2^2 = 8

Standard deviation of demand when demand of two retailers are combined = Square root ( 8 ) = 2 x square root ( 2 )

Answer to question 3:

Safety stock should be kept = Z value x New standard deviation of demand x Square root ( lead time) = 1.414x 2x square root ( 2 ) x square root( 2) = 1.414 x 2 x 2 = 5.656

Answer to question 4 :

Impact of integration is proportionately amount of safety stock required reduces. For example safety stock for 1 retailer 4.637. Accordingly , safety stock for 2 retailers = 4.637 x 2 = 9.274. However safety stock is only 5.656

If 30 stores were combined,

Average demand = 12

Standard deviation of combined demand = 2 x Square root ( 30 ) = 2 x 5.477 = 10.954

Safety stock = Z value x standard deviation x square root ( Lead time) = 1.64 x 10.954x square root ( 2 ) = 25.405

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a...
Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a normal distribution with a mean of 23 gallons per week and a standard deviation of 4.0 gallons per week. The new manager desires a service level of 90 percent. Lead time is 3 days, and the dairy is open seven days a week. (Hint: Work in terms of weeks.) If we use periodic inventory system, the time from delivery of an order until next...
Ray's Satellite Emporium wishes to determine the best order size for its best-selling satellite dish. Ray...
Ray's Satellite Emporium wishes to determine the best order size for its best-selling satellite dish. Ray has estimated that weekly demand for this model to be 25 units with a standard deviation of 5 units. His cost to carry one unit is $50 per year and the cost of placing an order with his supplier is $25. He's open 52 weeks a year. Assume weekly demand is normally distributed. (4 pts each) a. What is Ray’s economic order quantity in...
A retailer is considering inventory management of one of its products with the annual demand of...
A retailer is considering inventory management of one of its products with the annual demand of 600 units (1 year = 50 weeks). The product is delivered directly from the manufacturer who guarantees that every order is delivered in 2 weeks. The retailer pays the manufacturer $150 per unit. Additionally, every time the manufacturer fills an order from the retailer, machine setup cost of $60 is charged on the retailer. Transportation from the manufacturer costs the retailer $40 per shipment...
A retailer is considering inventory management of one of its products with the annual demand of...
A retailer is considering inventory management of one of its products with the annual demand of 600 units (1 year = 50 weeks). The product is delivered directly from the manufacturer who guarantees that every order is delivered in 2 weeks. The retailer pays the manufacturer $150 per unit. Additionally, every time the manufacturer fills an order from the retailer, machine setup cost of $60 is charged on the retailer. Transportation from the manufacturer costs the retailer $40 per shipment...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units a week, and safety stock is 200 units. What is the average inventory if 10 weeks’ supply is ordered at one time? What is the order point? The standard deviation of demand during the lead time is 100 units. Calculate the safety stock required for the following service levels: 75%, 80%, 85%, 90%, 95%, and 99.99%. Calculate the change in safety stock required to...
Choose the right answer: A product’s usage is normally distributed with average demand of 400 units/day...
Choose the right answer: A product’s usage is normally distributed with average demand of 400 units/day and a weekly standard deviation of 125. The product’s lead time is 20 days. Currently, the reorder point for this product is 8,200. The company work 5 days per week. If the company would like to have a service level of 95% for this product then A. it must decrease its safety stock by approximately 412 units. B. it must decrease its safety stock...
Daily demand for neckties at a MegaMart store is normally distributed with a mean of 20...
Daily demand for neckties at a MegaMart store is normally distributed with a mean of 20 units and a standard deviation of 7. The supplier, Suits Galore, takes on average about 9 days to supply a MegaMart order. The standard deviation of lead time is 3 days. MegaMart is targeting a customer service level of 95 percent (z = 1.65) and monitors its inventory continuously. How much safety inventory of neckties should MegaMart carry? What should their reorder point (ROP)...
Use the information in the following table to answer the questions below: Demand 100 units per...
Use the information in the following table to answer the questions below: Demand 100 units per week Standard deviation of weekly demand 10 units Average lead time 10 days Standard deviation of the lead time 5 days Cycle service level 70 % Considering a continuous review system, Find the standard deviation of demand during the lead time. Find the safety stock. What is the reorder point?
Weekly demand for the latest TV set at a retailer is normally distributed with a mean...
Weekly demand for the latest TV set at a retailer is normally distributed with a mean of 600 TVs and a standard deviation of 150. Currently, the store places orders to the supplier with a reorder point of 1,500 Tvs. Replenishment lead time is 2 weeks, fixed order cost per order is $200, each TV the retailer $300, and the inventory holding cost is 25% per year. If the retailer wants to achieve a 99% service level (use the z-value...
OM 540: Supply Chain Management Assignment 6: Inventory and Risk Pooling                               &
OM 540: Supply Chain Management Assignment 6: Inventory and Risk Pooling                                                                                                                                                                          Question #1 Harley-Davidson has its engine assembly plant in Milwaukee, and its motorcycle assembly plant in York, Pennsylvania. Engines are transported between the two plants using trucks, with each trip costing $1,600.  The motorcycle plant assembles and sells 100 motorcycles each day. (Assume 300 workdays in a year.)  Each engine costs $600, and Harley incurs a holding cost of 25 percent per year. How many engines should Harley load onto...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT