Use the table below to answer the questions 25 to 28.
Activity |
Optimistic duration |
Pessimistic duration |
Most Likely duration |
Weighted duration |
Immediate Predecessor |
P |
15 |
27 |
21 |
- |
|
Q |
18 |
36 |
24 |
P |
|
R |
26 |
40 |
24 |
P |
|
S |
21 |
39 |
27 |
Q |
|
T |
27 |
33 |
24 |
Q,R |
|
U |
16 |
32 |
24 |
S,T |
|
V |
16 |
30 |
26 |
U |
Calculate the actual duration of each activity (fill-in the table)
Draw an AOA network diagram for the activities (in the space below):
State the minimum duration of the project. ……………………………………………….
State the ES and LS time of activity T …………………………………………………….
The AOA network diagram is as below:-
The duration of different activities are as below:-
Activity |
Optimistic |
Most Probable |
Pessimistic |
Expected completion time |
Expected completion time |
P |
15 |
27 |
21 |
(15+4*27+21)/6 |
24.00 |
Q |
18 |
36 |
24 |
(18+4*36+24)/6 |
31.00 |
R |
26 |
40 |
24 |
(26+4*40+24)/6 |
35.00 |
S |
21 |
39 |
27 |
(21+4*39+27)/6 |
34.00 |
T |
27 |
33 |
24 |
(27+4*33+24)/6 |
30.50 |
U |
16 |
32 |
24 |
(16+4*32+24)/6 |
28.00 |
V |
16 |
30 |
26 |
(16+4*30+26)/6 |
27.00 |
Formula for Expected completion time = (O+4M+P)/6 |
ES of activity T= 59 (from the diagram)
LS of activity T=59 (from the diagram)
Get Answers For Free
Most questions answered within 1 hours.