Between the process Control Limits. |
||
Between the process Spec Limits. |
||
That allow 99.7% of the data points in the process |
||
None of the above answers are correct |
1. |
Cost-added activity |
|
2. |
Value-add activity |
|
3. |
Direct labor |
|
4. |
MRO |
1. |
D |
|
2. |
M |
|
3. |
A |
|
4. |
I |
|
5. |
C |
Moving materials downstream in the supply chain |
||
Moving materials upstream in the supply chain |
||
Moving materials both directions in a supply chain |
||
None of the above answers are correct |
1. |
Calculate root cause of process data |
|
2. |
Do not tell you root cause without brainstorming |
|
3. |
Are process tools that help calculate Kaizen |
|
4. |
None of the above are correct |
1st question
Correct answer is None of the above answers are correct
Six Sigma is named such because at the correct standard, there are six standard deviations (3 above mean and 3 below mean) that pass only 3.4 defects per million defect opportunities
2nd question
Correct answer is 1.Cost-added activity
Inspection in an operation is considered a non-value added activity that adds to the cost
3rd question
Correct answer is 2. M
M or measure phase is responsible for establishing management systems and regularly measuring process results against the goal of the project
4th question
Correct answer is Moving materials downstream in the supply chain
Reverse Logistics is moving materials downstream in the supply chain
5th question
Correct answer is 1.Calculate root cause of process data