A truck has a cycle time of 45 minutes and will transport 8 CY each trip. The truck is being loaded by a loader with a 2 cubic yard bucket with a 4 minute cycle time per bucket with a fill factor of 1.0. What would be the maximum number of trucks to use for this project?
In order to calculate the maximum number of trucks, we find the time to fill one truck and make sure in the cycle time of a truck the loader is used completely.
Time to load one truck = Time to load one basket * Number of times a bucket needs to be used
Number of times a bucket needs to be used = Capacity of truck / (Capacity of one bucket * Fill factor)
= 8/(2*1)
= 4
Time to load one truck = 4 minutes * 4
= 16 minutes
Cycle time of truck = 45 minutes
Number of trucks filled in 45 minutes = 45/16 = 2.8125
Thus the optimal maximum number of trucks will be 3 trucks