Question

Use the information in the following table to answer the questions below: Demand 100 units per...

  1. Use the information in the following table to answer the questions below:

Demand

100 units per week

Standard deviation of weekly demand

10 units

Average lead time

10 days

Standard deviation of the lead time

5 days

Cycle service level

70 %

Considering a continuous review system,

    1. Find the standard deviation of demand during the lead time.
    2. Find the safety stock.
    1. What is the reorder point?

Homework Answers

Answer #1
demand per week 100.00
Lead time, LT 10.0
Order quantity, Q= √(2*S*D/H) 141
standard deviation of weekly demand, Sd 10.0
standard deviation of lead time, SLT 5.00
Answer a. Standard deviation of lead time demand, SdLT SQRT((LT*(Sd)^2) + (d*SLT)^2)) 501.00
Service level desired 70.0%
Z value at service level, z NORMSINV(service probability) 0.52
Answer b Safety stock, SS z*SdLT 263
Lead Time Demand ( LT * daily Demand) 1000
Answer c Reorder point Lead time demand+Safety stock 1263
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
(a) The demand for item X is estimated to be normally distributed with a mean demand...
(a) The demand for item X is estimated to be normally distributed with a mean demand of 300 units per day and a standard deviation of 20 units per day. What is the reorder point and safety stock under continuous review policy? (Assume 95% service level, z (0.95) =1.65) (b) The supplier has changed. All costs remain the same, but lead time changes from 3 days to 30 days.What would be the new reorder point and safety stock? What do...
Choose the right answer: A product’s usage is normally distributed with average demand of 400 units/day...
Choose the right answer: A product’s usage is normally distributed with average demand of 400 units/day and a weekly standard deviation of 125. The product’s lead time is 20 days. Currently, the reorder point for this product is 8,200. The company work 5 days per week. If the company would like to have a service level of 95% for this product then A. it must decrease its safety stock by approximately 412 units. B. it must decrease its safety stock...
compute the reorder point when weekly demand is 100 units, lead time is 2 weeks, the...
compute the reorder point when weekly demand is 100 units, lead time is 2 weeks, the desired service level is 98% (which corresponds to z-2.06, standard deviations from the mean) and the standard deviation of demand during lead time is 30 units.
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units a week, and safety stock is 200 units. What is the average inventory if 10 weeks’ supply is ordered at one time? What is the order point? The standard deviation of demand during the lead time is 100 units. Calculate the safety stock required for the following service levels: 75%, 80%, 85%, 90%, 95%, and 99.99%. Calculate the change in safety stock required to...
Wong Enterprises used a Continuous Review System (i.e., Q System) for controlling inventory for a specific...
Wong Enterprises used a Continuous Review System (i.e., Q System) for controlling inventory for a specific end-item. The firm operates 5 days per week and 52 weeks a year and the end-item has the following characteristics:             Demand (D) = 20,020 units/year             Ordering Costs (S) = $40/order             Holding Costs = $1/unit/six months             Leadtime (L) = 10 days             Cycle Service Level = 94.95%             Assume that Demand is normally distributed; with Standard Deviation of weekly demand =...
Jake, Inc. begins a review of ordering policies for its continuous review system by checking the...
Jake, Inc. begins a review of ordering policies for its continuous review system by checking the current policies for a sample of its A items. Following are the characteristics of one item: Demand (D) = 94 units/week (assume 52 weeks per year) Ordering and setup cost (S) = $720/order Holding cost (H) = $23/unit/year Lead time (L) = 3 weeks Standard deviation of weekly demand = 30 units Cycle-service level = 82 percent Develop the best policies for a periodic-review...
Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a...
Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a normal distribution with a mean of 23 gallons per week and a standard deviation of 4.0 gallons per week. The new manager desires a service level of 90 percent. Lead time is 3 days, and the dairy is open seven days a week. (Hint: Work in terms of weeks.) If we use periodic inventory system, the time from delivery of an order until next...
The daily demand for 60” flat-screen TVs at the Sterling Archer’s discount warehouse is normally distributed...
The daily demand for 60” flat-screen TVs at the Sterling Archer’s discount warehouse is normally distributed with a mean of 5 units and a standard deviation of 5 units. The lead time for receiving a shipment of new TVs is 10 days and is fairly consistent. Determine the reorder point and safety stock for service levels of 90%, 95%, and 98%.
The annual demand for a product is 15,900 units. The weekly demand is 306 units with...
The annual demand for a product is 15,900 units. The weekly demand is 306 units with a standard deviation of 80 units. The cost to place an order is $33.50, and the time from ordering to receipt is eight weeks. The annual inventory carrying cost is $0.10 per unit. a. Find the reorder point necessary to provide a 99 percent service probability. (Use Excel's NORMSINV() function to find the correct critical value for the given α-level. Round "z" value to...
Lead Time Demand for an item we keep in stock is 420 units, with a standard...
Lead Time Demand for an item we keep in stock is 420 units, with a standard deviation of 44 units. What service level is achieved with our current Reorder point of 442 units? What Reorder Point should be used in order to accomplish a service level of 97%?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT