You're managing an inspection bench at Trikes and have been tasked to determine your set up time for a particular component. | ||||||||
You've been given the following information | ||||||||
Annual Demand | 39,000 | units | ||||||
Daily Demand | 150 | units | ||||||
Daily Production | 1,000 | units | ||||||
Desired Lot Lize | 150 | units | ||||||
Holding cost per unit per year | $10.00 | |||||||
set up labor cost per hour | $40.00 | |||||||
As per Economic Production quantity ( EPQ ) model ,
L = square root ( 2 x Cs x D / Ch x ( 1 – d/p))
Or, 150 = Square root ( 2 x Cs x 39000/ 10 x ( 1 – 150/1000))
Or, 150 = Square root ( 78000.Cs / 10 x 0.85)
Or, 150 = Square root ( 9176.47.Cs)
Or, 9176.47.Cs = 150 x 150
Or, Cs = 150 x 150/9176.47
Or, 2.45
Therefore , set up cost = $2.45
Set up labour cost per hour = $40
Therefore set up time = 2.45/40 hour = 2.45x 60/40 minutes = 3.675 minutes
SET UP TIME = 3.675 MINUTES |