Question

Using ? = 0.5 and the following data, compute exponential smoothing forecasts for periods 2 through...

Using ? = 0.5 and the following data, compute exponential smoothing forecasts for periods 2 through 8. (Round your intermediate calculations and final answers to 2 decimal places.) Period: 1 2 3 4 5 6 7 Forecast: 10 Actual demand: 12 15 11 13 11 11 10

Homework Answers

Answer #1

Forecast Period/Time = T

Forecast = F

Smoothing Constant = ?

Actual demand value to be forecasted = A

Formula to calculate Forecasted Value = Ft = Ft-1 + ? ( At-1 - Ft-1 )

Answer forcast for 8 period = 10.69 = Find the calculation below

Period Actual Demand Forecast Forecast
1 12 10 10
2 15 B2*0.5+(1-0-5)*C2 11
3 11 B3*0.5+(1-0-5)*C3 13
4 13 B4*0.5+(1-0-5)*C4 12
5 11 B5*0.5+(1-0-5)*C5 12.5
6 11 B6*0.5+(1-0-5)*C6 11.75
7 10 B7*0.5+(1-0-5)*C7 11.38
8 B8*0.5+(1-0-5)*C8 10.69
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Following are time-series data for ten different periods. Use exponential smoothing to forecast the values for...
Following are time-series data for ten different periods. Use exponential smoothing to forecast the values for periods 3 through 10. Use the value for the first period as the forecast for the second period. Compute forecasts using α = 0.8. Compute the MAD and MSE. Time period Value 1 27 2 31 3 58 4 63 5 59 6 66 7 71 8 86 9 101 10 97
In Excel, create forecasts for periods 6-13 using each of the following methods: 5 period simple...
In Excel, create forecasts for periods 6-13 using each of the following methods: 5 period simple moving average; 4 period weighted moving average (0.63, 0.26, 0.08, 0.03); exponential smoothing (alpha = 0.23 and the forecast for period 5 = 53); linear regression with the equation based on all 12 periods; and quadratic regression with the equation based on all 12 periods.  Round all numerical answers to two decimal places. The actual values for 12 periods (shown in order) are: (1) 45  (2)...
The actual values for 12 periods (listed in order, 1-12). In Excel, create forecasts for periods...
The actual values for 12 periods (listed in order, 1-12). In Excel, create forecasts for periods 6-13 using each of the following methods: 5 period simple moving average; 4 period weighted moving average (0.63, 0.26, 0.08, 0.03); exponential smoothing (alpha = 0.23 and the forecast for period 5 = 53); linear regression with the equation based on all 12 periods; and quadratic regression with the equation based on all 12 periods.  Round all numerical answers to two decimal places. A. The...
Following are time-series data for ten different periods. Use exponential smoothing to forecast the values for...
Following are time-series data for ten different periods. Use exponential smoothing to forecast the values for periods 3 through 10. Use the value for the first period as the forecast for the second period. Compute forecasts using α = 0.1. Compute the MAD and MSE. Time period Value 1 27 2 31 3 58 4 63 5 59 6 66 7 71 8 86 9 101 10 97 Group of answer choices A) MAD=296.6, MSE=1266.5 B) MAD=296.6 , MSE=11398.5 C)...
Following are time-series data for ten different periods. Use exponential smoothing to forecast the values for...
Following are time-series data for ten different periods. Use exponential smoothing to forecast the values for periods 3 through 10. Use the value for the first period as the forecast for the second period. Compute forecasts using α = 0.8. Compute the MAD and MSE. Time period Value 1 27 2 31 3 58 4 63 5 59 6 66 7 71 8 86 9 101 10 97 Group of answer choices a) MAD=9.7, MSE=1585.6 b) MAD=9.7, MSE=176.2 c) MAD=10.2,...
Instructions The Data contains the actual values for 12 periods (listed in order, 1-12). In Excel,...
Instructions The Data contains the actual values for 12 periods (listed in order, 1-12). In Excel, create forecasts for periods 6-13 using each of the following methods: 5 period simple moving average; 4 period weighted moving average (0.63, 0.26, 0.08, 0.03); exponential smoothing (alpha = 0.23 and the forecast for period 5 = 53); linear regression with the equation based on all 12 periods; and quadratic regression with the equation based on all 12 periods.  Round all numerical answers to two...
Instructions The Data contains the actual values for 12 periods (listed in order, 1-12). In Excel,...
Instructions The Data contains the actual values for 12 periods (listed in order, 1-12). In Excel, create forecasts for periods 6-13 using each of the following methods: 5 period simple moving average; 4 period weighted moving average (0.63, 0.26, 0.08, 0.03); exponential smoothing (alpha = 0.23 and the forecast for period 5 = 53); linear regression with the equation based on all 12 periods; and quadratic regression with the equation based on all 12 periods.  Round all numerical answers to two...
After plotting demand for four periods, an emergency room manager has concluded that a trend-adjusted exponential...
After plotting demand for four periods, an emergency room manager has concluded that a trend-adjusted exponential smoothing model is appropriate to predict future demand. The initial estimate of trend is based on the net change of 19 for the three periods from 1 to 4, for an average of +6.33 units. Period Actual Period Actual 1 202 6 251 2 221 7 266 3 216 8 276 4 221 9 281 5 241 10 Use α=.50 and β=.10, and TAF...
After plotting demand for four periods, an emergency room manager has concluded that a trend-adjusted exponential...
After plotting demand for four periods, an emergency room manager has concluded that a trend-adjusted exponential smoothing model is appropriate to predict future demand. The initial estimate of trend is based on the net change of 23 for the three periods from 1 to 4, for an average of +7.67 units. Period Actual Period Actual 1 208 6 261 2 231 7 276 3 226 8 286 4 231 9 291 5 251 10 Use α=.60 and β=.15, and TAF...
Question 1 contains the actual values for 12 periods (listed in order, 1-12). In Excel, create...
Question 1 contains the actual values for 12 periods (listed in order, 1-12). In Excel, create forecasts for periods 6-13 using each of the following methods: 5 period simple moving average; 4 period weighted moving average (0.63, 0.26, 0.08, 0.03); exponential smoothing (alpha = 0.23 and the forecast for period 5 = 53); linear regression with the equation based on all 12 periods; and quadratic regression with the equation based on all 12 periods. Round all numerical answers to two...