Question

Lead Time Demand for an item we keep in stock is 420 units, with a standard...

  1. Lead Time Demand for an item we keep in stock is 420 units, with a standard deviation of 44 units.
  1. What service level is achieved with our current Reorder point of 442 units?
  1. What Reorder Point should be used in order to accomplish a service level of 97%?

Homework Answers

Answer #1

Lead time demand = d * L = 420 units

Std. Deviation = = 44 units

a) Reorder point = 442 units

Reorder point = Lead time demand + Z * Std. Deviation

442 = 420 + Z * 44

Z = 0.5

For Z = 0.5, Service level = 69.14%

b) For Service level of 97%, Z value = 1.88

Reorder point = Lead time demand + Z * Std. Deviation = 420 + 1.88 * 44 = 502.72 = 503 units

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.

If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
compute the reorder point when weekly demand is 100 units, lead time is 2 weeks, the...
compute the reorder point when weekly demand is 100 units, lead time is 2 weeks, the desired service level is 98% (which corresponds to z-2.06, standard deviations from the mean) and the standard deviation of demand during lead time is 30 units.
(a) The demand for item X is estimated to be normally distributed with a mean demand...
(a) The demand for item X is estimated to be normally distributed with a mean demand of 300 units per day and a standard deviation of 20 units per day. What is the reorder point and safety stock under continuous review policy? (Assume 95% service level, z (0.95) =1.65) (b) The supplier has changed. All costs remain the same, but lead time changes from 3 days to 30 days.What would be the new reorder point and safety stock? What do...
An inventory item of XYZ Manufacturing has an average daily demand of 10 units with a...
An inventory item of XYZ Manufacturing has an average daily demand of 10 units with a maximum daily demand of 12 units. The economic order quantity is 200 units. Without safety stocks, the reorder point is 50 units. Safety stocks are set at 94 units. Required: a. Determine the reorder point with safety stocks. b. Determine the maximum inventory level. c. Determine the average lead time. d. Determine the maximum lead time
Use the information in the following table to answer the questions below: Demand 100 units per...
Use the information in the following table to answer the questions below: Demand 100 units per week Standard deviation of weekly demand 10 units Average lead time 10 days Standard deviation of the lead time 5 days Cycle service level 70 % Considering a continuous review system, Find the standard deviation of demand during the lead time. Find the safety stock. What is the reorder point?
The reorder point r = dm is defined as the lead-time demand for an item. In...
The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order quantity model with...
Q. Daily demand for a product is normally distributed with a mean M= 12 units and...
Q. Daily demand for a product is normally distributed with a mean M= 12 units and standard deviation Q= 4 units. Lead time is 9 days. The order quantity for this item is set at a 12-day supply. a. If a minimum probability of satisfying demand per cycle of 0.80 is desired, what is the reorder point? b. If a fill rate of 9% is desired, what is the reorder point?
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units a week, and safety stock is 200 units. What is the average inventory if 10 weeks’ supply is ordered at one time? What is the order point? The standard deviation of demand during the lead time is 100 units. Calculate the safety stock required for the following service levels: 75%, 80%, 85%, 90%, 95%, and 99.99%. Calculate the change in safety stock required to...
The annual demand for a product is 15,900 units. The weekly demand is 306 units with...
The annual demand for a product is 15,900 units. The weekly demand is 306 units with a standard deviation of 80 units. The cost to place an order is $33.50, and the time from ordering to receipt is eight weeks. The annual inventory carrying cost is $0.10 per unit. a. Find the reorder point necessary to provide a 99 percent service probability. (Use Excel's NORMSINV() function to find the correct critical value for the given α-level. Round "z" value to...
4) One item a computer store sells is supplied by a vendor who handles only that...
4) One item a computer store sells is supplied by a vendor who handles only that item. Demand for that item recently changed, and the store manager must determine when to replenish it. The manager wants a probability of at least 96 percent of not having a stockout during lead time. The manager expects demand to average a dozen units a day and have a standard deviation of 3 units a day. Lead time is variable, averaging 3 days with...
Problem 14-3 (Algorithmic) The reorder point r = dm is defined as the lead-time demand for...
Problem 14-3 (Algorithmic) The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT