Question

A productivity and accuracy audit recently occurred of the three release of information staff that report...

A productivity and accuracy audit recently occurred of the three release of information staff that report to you. Below are the results of the study:

Productivity

Accuracy Rate

ROI One

24 charts in 8 hours

95%

ROI Two

20 charts in 8 hours

90%

ROI Three

30 charts in 8 hours

90%

Your department currently receives release requests for 100 charts per day. Using the audit results, AHIMA’s benchmarking standard, and compliance guidelines, develop feedback for each of the ROI staff. Your feedback to each staff member should be positive and comprehensive. Feedback must address at least productivity, accuracy, and suggestions for improvement. During this process, the department director has asked you to evaluate if you have enough staff to maintain the workload and to make recommendations for a change in staffing if necessary. Develop a proposal for staffing change if necessary.

Homework Answers

Answer #1

Average productivity = 100*8/24=33.33 charts in 8 hours

Average ROI productivity =33.33/3=11.11 charts in 8 hours

Average accuracy = (95+90+90)/3=91.66%

ROI One

The process is self-sufficient with the productivity and accuracy above the average established levels. Process documentation is appropriate thereby allowing the consistency in production to be preserved.

ROI Two

This process has attained the required productivity level. The accuracy level on the contrary lags behind the average rate necessary for system sustainability. Possible improvements include shifting focus and resources to increasing the accuracy rate by one level.

ROI Three

Productivity in this case is the highest for all levels in this category. The accuracy rate is however, a level below the average system level. A slight reduction in productivity may allow space for accuracy improvements.

The current employees are adequate for the production process. Possible improvements include developing process metrics that will measure productivity levels and allow comparison to prior periods acting as a benchmark for further improvements

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A productivity and accuracy audit recently occurred of the two scanning staff that report to you....
A productivity and accuracy audit recently occurred of the two scanning staff that report to you. Below are the results of the study: Productivity Accuracy Rate Scanner One 60 charts in 8 hours 95% Scanner Two 100 charts in 8 hours 75% Your department currently receives on the average 200 charts per day that need to be scanned. Your facility compliance guidelines state that scanners should maintain at least a 95% accuracy rate. Using the audit results, AHIMA’s benchmarking standard,...
1.Establishing the virtual Management: As known, managing virtual staff requires a different method or approach than...
1.Establishing the virtual Management: As known, managing virtual staff requires a different method or approach than managing local staff. Due to that reason, Golden Scent has developed a strategic plan to successfully manage its virtual staff in the USA. Identify the suitable manager. to make sure our work will proceed as we planned, Golden Scent willrecruit a virtual manager with the essential skills and knowledge required to manage virtual employees. Find the skilled people to work with. Since not everyone...
Sign In INNOVATION Deep Change: How Operational Innovation Can Transform Your Company by Michael Hammer From...
Sign In INNOVATION Deep Change: How Operational Innovation Can Transform Your Company by Michael Hammer From the April 2004 Issue Save Share 8.95 In 1991, Progressive Insurance, an automobile insurer based in Mayfield Village, Ohio, had approximately $1.3 billion in sales. By 2002, that figure had grown to $9.5 billion. What fashionable strategies did Progressive employ to achieve sevenfold growth in just over a decade? Was it positioned in a high-growth industry? Hardly. Auto insurance is a mature, 100-year-old industry...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT