Question

Question: A project manager has anticipated several scenarios that might adversely affect the cost of the...

Question: A project manager has anticipated several scenarios that might adversely affect the cost of the project. In response, the project manager has allocated money to address these issues should they occur. What is the component of the budget called?

Answer choices: Padding the budget

Contingency reserves

Management reserves

Activity cost estimates

Homework Answers

Answer #1

Answer: The given options are evaluated as follows :

  • Padding the Budget - Making the budget larger than the actual estimates for a project either by increasing cost or reducing revenue from a project. Not related to any contingency and hence, this option is rejected.
  • Contingency reserves - Reserve created to offset for anticipated future scenarios if they occur. It is used to provide for unfavorable changes in the project cost. Hence, this is the correct option.
  • Management reserves- A receive created to account for unforeseen events. Generally based on the cost of the project. This option is also rejected as it involves accounting for unforeseen events and not anticipated losses.
  • Activity Cost Estimates - A process to determine the costs that may be incurred to complete a specific activity in a project. Not related to any future scenarios, hence this option is also rejected.

Conclusion: “Contingency Reserves “ is the correct answer.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Question: Based on the WBS for a project with the requirement to lower a restaurant’s food...
Question: Based on the WBS for a project with the requirement to lower a restaurant’s food cost, preliminary work performance date indicate that the initial target has not ben achieved. The project manager is reviewing suggestions to identify suitable actions for closing the gap. Once the desired scope change has been selected, the project manager will update the project plan. Which scope describes the actions that the project manager should take? Answer Choices: The change in scope is funded in...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the project managers....
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the project managers....
CASE STUDY Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company...
CASE STUDY Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the...
CAPITAL BUDGETING PROJECT NEWMAN ENTERPRISES, Inc. is a multinational conglomerate corporation providing a wide range of...
CAPITAL BUDGETING PROJECT NEWMAN ENTERPRISES, Inc. is a multinational conglomerate corporation providing a wide range of goods and services to its customers. As part of its budgeting process for the next year, it has three mutually exclusive projects under consideration, and it might decide which project should receive the investment funds for this year. As part of the financial analysis team, it is up to you to determine the appropriate valuation of each project. However, before you can determine the...
Internal and External Linkages, Strategic Cost Management Maxwell Company produces a variety of kitchen appliances, including...
Internal and External Linkages, Strategic Cost Management Maxwell Company produces a variety of kitchen appliances, including cooking ranges and dishwashers. Over the past several years, competition has intensified. In order to maintain—and perhaps increase—its market share, Maxwell’s management decided that the overall quality of its products had to be increased. Furthermore, costs needed to be reduced so that the selling prices of its products could be reduced. After some investigation, Maxwell concluded that many of its problems could be traced...
Economic inequality is a huge issue. A recent study found that the world’s 80 wealthiest individuals...
Economic inequality is a huge issue. A recent study found that the world’s 80 wealthiest individuals own as much as the entire world’s poorest 3.5 billion people. The richest 1 percent of the world’s population control half of the world’s total wealth. Many individuals, corporations, charities, and government agencies have projects and programs in place to attempt to tackle this and other important global issues such as sustainability, but there are many opportunities to do more. A grassroots group of...