Question: Project was given a fixed budget to complete by a certain date, but project is running behind. Which triple constraint can the project team adjust to complete the project on schedule? Answer Choices: Time, Risk, Cost, Scope
The triple constraint that the project team can adjust to complete the project on the schedule includes Time.
Triple constraint is a model of the constraints essential in managing a project. It says that the success of the project can be impacted by its budget, deadlines, and features. as the project is running behind the due date, the component of triple constraint that the team must adjust to complete the project on schedule is time. Time constraint describes the total time required for the completion of each part of the project that can be managed by the team.