Question

Question: The project’s progress has fallen behind schedule on the critical path. The project manager has...

Question: The project’s progress has fallen behind schedule on the critical path. The project manager has decided to recover the schedule by crashing the project’s schedule. What is the expected consequence of this project’s triple constraints?

Homework Answers

Answer #1

Time, scope and cost are three constraints of the project which need to be balanced to ensure that the project is completed to the best satisfaction of the customers while keeping within all three constraints as much as possible.

Effect of crashing on the project will be as follows.

(i) Scope- The scope is related to the deliverables and quality of the project. The decision of crashing should not impact the scope of project, because doing this will affect the deliverable quality, which is not recommended, because it will affect customer satisfaction.

(ii) Time - The time needs to be shortened because the project needs to be completed as per schedule and currently is behind schedule.

(iii) Cost- The cost is going to increase because in order to complete the remaining work in shorter time, more resources will have to be deployed, which will increase the cost.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
Question: A project manager has anticipated several scenarios that might adversely affect the cost of the...
Question: A project manager has anticipated several scenarios that might adversely affect the cost of the project. In response, the project manager has allocated money to address these issues should they occur. What is the component of the budget called? Answer choices: Padding the budget Contingency reserves Management reserves Activity cost estimates
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
ABC Corporation is considering an expansion project. The proposed project has the following features: The project...
ABC Corporation is considering an expansion project. The proposed project has the following features: The project has an initial cost of $1,000,000 (machine: $800,000, insurance: $40,000, shipping $60,000, modification: $100,000) --this is also the amount which can be depreciated using the following 3 year MACRS depreciation schedule: Year Depreciation Rate 1 33% 2 45% 3 15% 4 7% The sales price and cost are both expected to increase by 4 percent per year due to inflation. If the project is...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Case Study 1: A Day in the Life Rachel, the project manager of a large information...
Case Study 1: A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal news....
Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine...
Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine activities involved. These activities have been labeled A through I in the following table. The company is planning to finish the project in 34 weeks. Please answer the following questions. Determine the expected (estimated) duration and variance for each activity. You can round the expected duration numbers without decimals. Activity Immediate Predecessor(s) Optimistic Probable Pessimistic Expected duration Variance A -- 5 9 13 Answer...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...