Question

Question: Based on the WBS for a project with the requirement to lower a restaurant’s food...

Question: Based on the WBS for a project with the requirement to lower a restaurant’s food cost, preliminary work performance date indicate that the initial target has not ben achieved. The project manager is reviewing suggestions to identify suitable actions for closing the gap. Once the desired scope change has been selected, the project manager will update the project plan. Which scope describes the actions that the project manager should take? Answer Choices: The change in scope is funded in the contingency allowance so the project manager should accept the variances in baselines for scope, time, and cost. The change in scope requires an update to the scope baseline, so the project manger should use the change control system to update the baselines for time and cost. The change in scope is funded in the budget for managerial reserves, so the project manage should draw upon the reserve to cover the variances in baselines for scope, time and cost. The project plan needs to remain unchanged, so the project manager should reject the essential scope change to avoid incurring contractual penalties because of a delay.

Homework Answers

Answer #1

Here, correct answer is The change in scope requires an update to the scope baseline, so the project manger should use the change control system to update the baselines for time and cost.

Explanation:

Once scope change is selected, Project manager will update to the scope baseline, as due to one change in scope, within the same baseline, there will have impact on other scope, hence, first, we should update scope baseline, then, being a project manager, I will use change control system or perform integrated change control as to update baselines for time and cost. Hence, correct answer is the change in scope requires an update to the scope baseline, so the project manger should use the change control system to update the baselines for time and cost. Other options are not relevant, so other options are eliminated.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
(Use the case of “Global Treps”) You have been selected as the project manager for the...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do several international Camp Noah projects. Last year the French government asked for resources for children in Southeastern France who had been affected by floods; LSS responded within 15 weeks with a French Camp Noah curriculum that met many of the project objectives. The Board of Directors of LSS commended the effort; international expansion was added to this year’s strategic objectives for the LSS organization....
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the project managers....
CASE STUDY Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company...
CASE STUDY Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the...