Given is a CPM project network diagram as shown below.
Activity |
Start |
A |
B |
C |
D |
E |
F |
G |
H |
End |
days |
0 |
2 |
6 |
8 |
3 |
4 |
2 |
3 |
2 |
0 |
a) The Project Completion time = ___ days.
b) The Earliest Start time, ES, of Activity G = ____ days.
c) The Latest Finish time, LF, of Acitivity C = ____ days.
d) The critical activities are = ____ (ex. Fill in answer as:
ABCD)
PLEASE GIVE POSITIVE FEEDBACK AND UP RATE MY ANSWER, THANK YOU.
Answer :
a) The Project Completion time = 19 days.
b) The Earliest Start time, ES, of Activity G =
14
days.
c) The Latest Finish time, LF, of Acitivity C =
10
days.
d) The critical activities are = ACEGH.
Explanation of finding time duration of above CPM project network diagram:
First Identify the Earliest Start time (ES) and Earliest Finish time (EF)
ES = The latest EF of the precedence activities ( (Which is directly dependent on each other)
EF = ES + Duration
For the last activity ES = LS and EF = LF
similarly , now work backward
LF = Earliest LS of the following activities (Which is directly dependent on each other)
LS = LF - Duration
All activities are critical for which ES = LS