A copy machine is available 18 hours a day. On a typical day, the machine needs...

A copy machine is available 18 hours a day. On a typical day, the machine needs to process 320 jobs. Each job takes about 1.5 minutes on the machine, 0.5 minute of which is processing time and 1 minute is setup time (logging in, defining the job). About 25% of the jobs need to be reworked, in which the set?up time and the processing time have to be repeated once. In the remaining time, the equipment is idle. You would need to show steps and use 2 decimals in calculations.

(a)[2] Draw a tree diagram to show the breakdown of equipment time. Alternatively, you can opt to draw a diagram like Figure 8.1 (page 214) to illustrate the breakdown of equipment time.

(b)[2] Define and calculate total non?value added time in minutes.

(c)[2] Define and calculate total value?added time in minutes.

(d)[3] Calculate total waste time in minutes. Give a detailed breakdown of waste time.

(e)[1] What is the OEE of the equipment? (percentage, 2 decimals, i.e. 23.67%)

Homework Answers

Answer #1

(b) Total available time = 18x60 =1080 min.

Total processing time = 320x0.5 = 160 min

Total set up time = 320x1 =320 min.

Total rework time = 320x0.25 ( 1+0.5) =120 min.

Total Non value added time = set up time + rework time = 320+120 = 440 min.

(c) Total value added time = processing time = 160 min.

(d) Total waste time = set up time + rework time + Idle time = 320+120+ 480 = 920 mn.

(e) OEE = processing time / time available = 160/1080 = 0.1481 = 14.81%

(a)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The admin office has one centralized copy machine located in a small room in the office....
The admin office has one centralized copy machine located in a small room in the office. Jobs arrive at this copy center according to a Poisson process at a mean rate of 2 per day. The processing time to perform each job has an exponential distribution with a mean of 1/4 day. Because the copy jobs are bulky, those not being worked on are currently being stored in a room some distance from the copy machine. However, to save time...
A bike frame has to go through the welding operation. The time in the welding operation...
A bike frame has to go through the welding operation. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 0.5 hour waiting for the setup of the machine, 2 hours waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 1.5 hours waiting for the transfer to the welding machine; then, at the welding machine, the...
Exercise 7A-1 Time-Driven Activity-Based Costing [LO 7-6] Saratoga Company manufactures jobs to customer specifications. The company...
Exercise 7A-1 Time-Driven Activity-Based Costing [LO 7-6] Saratoga Company manufactures jobs to customer specifications. The company is conducting a time-driven activity-based costing study in its Purchasing Department to better understand how Purchasing Department labor costs are consumed by individual jobs. To aid the study, the company provided the following data regarding its Purchasing Department and three of its many jobs: Number of employees 20 Average salary per employee $ 25,000 Weeks of employment per year 52 Hours worked per week...
Consider a batch manufacturing process in which a machine processes jobs in batches of three units....
Consider a batch manufacturing process in which a machine processes jobs in batches of three units. The process starts only when there are three or more jobs in the buffer in front of the machine. Otherwise, the machine stays idle until the batch is completed. Assume that job interarrival times are uniformly distributed between 2 and 8 hours, and batch service times are uniformly distributed between 5 and 15 hours. Assuming the system is initially empty, simulate the system manually...
please post solutions using R Consider a batch manufacturing process in which a machine processes jobs...
please post solutions using R Consider a batch manufacturing process in which a machine processes jobs in batches of three units. The process starts only when there are three or more jobs in the buffer in front of the machine. Otherwise, the machine stays idle until the batch is completed. Assume that job interarrival times are uniformly distributed between 2 and 8 hours, and batch service times are uniformly distributed between 5 and 15 hours. Assuming the system is initially...
Question: On the Level Construction Company has been growing and needs to purchase a new machine....
Question: On the Level Construction Company has been growing and needs to purchase a new machine. They have been researching multiple companies and have narrowed down their choices to two options - based on reliability and customer service. They now need the help of accounting to determine which option is better financially. Company 1 - Millipede The equipment would cost $3,000,000 up front. It has a 12 year useful life. Millipede's equipment would allow for 2 additional construction jobs per...
Case Study 1: A Day in the Life Rachel, the project manager of a large information...
Case Study 1: A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal news....
1. Aztec Builders allocates manufacturing overhead to jobs based on machine hours. The company has the...
1. Aztec Builders allocates manufacturing overhead to jobs based on machine hours. The company has the following estimated costs for the upcoming year: Direct materials used $25,000 Direct labour costs $62,000 Salary of factory supervisor $50,000 Advertising expense $33,000 Heating and lighting costs for factory $51,000 Depreciation on factory equipment $19,000 Sales commissions $8,000 The firm estimates that 1,800 direct labour hours will be worked in the upcoming year, while 2,000 machine hours will be used during the year. The...
Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton,...
Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton, Illinois. Recently hired general manager, Bob Behar, is concerned about the large inventories and manufacturing inefficiencies in the plant. The Paxton plant has two separate assembly lines – one for chairs and one for tables. Demand for chairs is significantly larger than tables, so Bob decides to tackle the table assembly process for first. Bob has recently hired a summer intern, Eileen Mayer, who...
ADVERTISEMENT