Question

A bike frame has to go through the welding operation. The time in the welding operation...

A bike frame has to go through the welding operation. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 0.5 hour waiting for the setup of the machine, 2 hours waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 1.5 hours waiting for the transfer to the welding machine; then, at the welding machine, the unit spends 2 hours waiting in front of the welding machine for the batch to start, 0.5 hour waiting for the setup of the welding machine, 2 hours waiting for the other pieces of the batch to go through welding, 1 minute at the welding machine, and 1 hour waiting for the transfer to the next department.

(a)[6] Calculate the exact total flow time in minutes of the welding operation.

(b)[2] Calculate the exact value added time in minutes of the welding operation.  

(c)[2] Calculate the value added percentage (percentage, 5 decimals, i.e. 1.54397%).

Homework Answers

Answer #1

Given,

Wait time before start =2 hrs

Setup time= 0.5 hrs

Wait time for other pieces to go through cutting= 2 hrs

Cutting time= 1 min = 1/60 hr =0.0166 hr

Transfer to welding wait time= 1.5 hrs

Welding wait time= 2 hrs

Welding setup time= 0.5 hrs

Wait for other pieces to go through welding= 2 hrs

Welding time= 1/60 hr = 0.0166 hr

Wait for transfer to next dept. = 1 hr

a) Exact flow time = wait time before start + setup time + wait time for other pieces to go through cutting + cutting time + transfer wait time + welding wait time + welding setup + wait for other pieces to go through welding + welding time + wait for transfer = 2+0.5+2+0.0166+1.5+2+0.5+2+0.0166+1 = 11.5332 hrs

b) Exact value added time = 1+ 1 = 2 mins = 2/60 hrs = 0.033 hr

c) value added percentage = (0.03333/11.5332) * 100 = 0.28899%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A copy machine is available 18 hours a day. On a typical day, the machine needs...
A copy machine is available 18 hours a day. On a typical day, the machine needs to process 320 jobs. Each job takes about 1.5 minutes on the machine, 0.5 minute of which is processing time and 1 minute is setup time (logging in, defining the job). About 25% of the jobs need to be reworked, in which the set?up time and the processing time have to be repeated once. In the remaining time, the equipment is idle. You would...
1. For a particular operation, the setup time is 10 minutes and the run time is...
1. For a particular operation, the setup time is 10 minutes and the run time is 50 minutes to produce a standard lot of 40 parts. It takes three additional hours to circulate a container of parts after production is completed. The demand rate is 20,000 parts per month. There are 160 production hours in a month. a. How many standard containers are needed? n = D(T) / C Use the following inputs: Demand rate (D) = ________ parts /...
Lead Time Audio Max Electronics Company manufactures electronic stereo equipment. The manufacturing process includes printed circuit...
Lead Time Audio Max Electronics Company manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of assembly time. After each batch is completed,...
Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC)...
Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed,...
MANAGERIAL ACCOUNTING Q1: The Klamath Corp. produces two products, saws and drills. Three activities are used...
MANAGERIAL ACCOUNTING Q1: The Klamath Corp. produces two products, saws and drills. Three activities are used in their manufacture. These activities and their associated costs and bases are as follows: Activity Budgeted Costs Activity Base Stamping $200,000 Machine hours Assembly $400,000 Labor hours Setup $30,000 Number of setups Activity Base Saws Drills Total Machine hours 4,000 6,000 10,000 Labor hours 7,000 13,000 20,000 Number of setups        3        12        15 Units produced     500     600 a. Determine the activity rate for each...
Reducir, Inc., produces two different types of hydraulic cylinders. Reducir produces a major subassembly for the...
Reducir, Inc., produces two different types of hydraulic cylinders. Reducir produces a major subassembly for the cylinders in the Cutting and Welding Department. Other parts and the subassembly are then assembled in the Assembly Department. The activities, expected costs, and drivers associated with these two manufacturing processes are given below. Process Activity Cost Activity Driver Expected Quantity Cutting and Welding Welding $ 776,000    Welding hours 4,000 Machining 450,000    Machine hours 10,000 Inspecting 448,250    No. of inspections 1,000 Materials handling 300,000...
1. 35 Solexes (motorized bicycles) are available at a bike rental. Each Solex has a 0.05...
1. 35 Solexes (motorized bicycles) are available at a bike rental. Each Solex has a 0.05 probability of being found to be dysfunctional. At a certain time, a group of 32 people want to go on a Solex tour. What is the probability that they can do this? 2. At the start of the month, there are 750 units of a given product in stock. Sales per month follow a normal distribution where μ = 700 and σ = 25...
Hammond Inc. has analyzed the setup time on its computer-controlled lathe. The setup requires changing the...
Hammond Inc. has analyzed the setup time on its computer-controlled lathe. The setup requires changing the type of fixture that holds a part. The average setup time has been 135 minutes, consisting of the following steps: Turn off machine and remove fixture from lathe 10 minutes Go to tool room with fixture 15 Record replacement of fixture to tool room 18 Return to lathe 20 Clean lathe 15 Return to tool room 20 Record withdrawal of new fixture from tool...
Hartselle enterprises manufactures a variety of hand-finished pottery. Each piece of pottery must go through two...
Hartselle enterprises manufactures a variety of hand-finished pottery. Each piece of pottery must go through two critical and relatively standardized processes: molding and firing. Crystal Hartselle, founder of the company, is also responsible for maintaining the company's accounting information system. She currently calculates overhead rates on a month basis. Crystal recently prepared the following data for last month: Monthly Costs + Quantities Direct Material 2,500 pounds ($0.75 per pound) Direct Labor 300 hours (Pay rate: $7.50 per hour plus benefits...
There is no solution for question 7.3 in the textbook Matching Supply with Demand. Third edition...
There is no solution for question 7.3 in the textbook Matching Supply with Demand. Third edition Bruno Fruscalzo decided to set up a small production facility in Sudney to sell at local restaurants that want gelato on their desser menu. To start simple, he would offer only three flavors of gelato: fragola( strawberry), chocolato (chocolate), and bacio (chocolate with hazelnut). After a short time he found his demand and setup times to be fragola chocolato bacio demand (kg/hr) 10 15...