The next set of questions use the following example:

A network consists of the activities in the following list. Times are given in weeks.

CAN ONLY BE ONE OF THE OPTIONS it's not 5 I tried that.

Activity

Preceding

Time

A

--

8

B

--

3

C

A

7

D

A,B

3

E

C

4

F

D

6

Draw the network diagram.

Calculate the ES, EF, LS, LF, and Slack for each activity.

Find the total project completion time.

What is the slack of activity B?

7
3
8
2

0

What is the LS of activity D?   

Week 8
Week 13
Week 10
Week 11
Week 7

Homework Answers

Answer #1

Solution:

(a) From the given information, network diagram can be drawn as below:

(b) From the network diagram, the ES, EF, LS and LF for each activity is computed below:

ES - Early Start

EF - Early Finish

LS - Late Start

LF - Late Finish

Slack is calculated as:

Slack = (LS - ES) or (LF - EF)

The computed values of ES, EF, LS, LF and Slack are summarized in the table below:

(c) Project completion time is given by the EF i.e. Early Finish time of the last activity. Here, the EF of last activity E is 19. Therefore,

Total project completion time = 19 weeks

From the above table:

(1) Slack of activity B = 7 weeks

(2) LS of activity D = Week 10

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What is the slack of activity B? 8 0 3 2 7
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
In the following table task durations are given in weeks. Use the three point to find:...
In the following table task durations are given in weeks. Use the three point to find: Activity Predecessor Optimistic Normal Pessimistic A None 2 4 6 B None 3 5 9 C A 4 5 7 D A 4 6 10 E B,C 4 5 7 F D 3 4 8 G E 3 5 8 Construct the (AON) Activity on Node network diagram Find each activity’s ES, EF, LS and LS Identify all paths. Which path is the critical...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)      &nbsp
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)          to           tml                tp                                 te     A                     -----                        1                      2                      3                           B                      A                           2                      4                      6     C                      B                            1                      4                      7     D                      B                            3                      4                      5     E                      C                            1                      3                      5     F                      D, E                       2                      3                      4 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.] 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time and the standard deviation (σ) for the project— round off the standard deviation to the nearest...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...