The next set of questions use the following example:
A network consists of the activities in the following list. Times are given in weeks.
CAN ONLY BE ONE OF THE OPTIONS it's not 5 I tried that.
Activity |
Preceding |
Time |
A |
-- |
8 |
B |
-- |
3 |
C |
A |
7 |
D |
A,B |
3 |
E |
C |
4 |
F |
D |
6 |
Draw the network diagram.
Calculate the ES, EF, LS, LF, and Slack for each activity.
Find the total project completion time.
What is the slack of activity B?
7 |
3 |
8 |
2 |
0 What is the LS of activity D?
|
Solution:
(a) From the given information, network diagram can be drawn as below:
(b) From the network diagram, the ES, EF, LS and LF for each activity is computed below:
ES - Early Start
EF - Early Finish
LS - Late Start
LF - Late Finish
Slack is calculated as:
Slack = (LS - ES) or (LF - EF)
The computed values of ES, EF, LS, LF and Slack are summarized in the table below:
(c) Project completion time is given by the EF i.e. Early Finish time of the last activity. Here, the EF of last activity E is 19. Therefore,
Total project completion time = 19 weeks
From the above table:
(1) Slack of activity B = 7 weeks
(2) LS of activity D = Week 10