Question

What is the crashing techniques used for? a. Activity sequencing b. Cost reduction c. Network diagramming...

What is the crashing techniques used for?

a.

Activity sequencing

b.

Cost reduction

c.

Network diagramming

d.

Duration compression

Homework Answers

Answer #1

The right option is D, Duration Compression as crashing is a technique used to "compress" or decrease the duration of a project while making sure not to incur higher costs. It is measure that is used when the fast-tracking process did not yield the desired results.

Activity sequencing is wrong as it is about finding the logical sequence of activities to carry out the project effectively.

Cost Reduction is wrong as it is about finding ways to cut costs and increase profits for the organization.

Network Diagramming is wrong as it is about making a graphical representation of all the tasks involved in completing a project.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
What is the term used for shortening a logic network after construction has begun? Crashing Fast...
What is the term used for shortening a logic network after construction has begun? Crashing Fast tracking Resource leveling Time-scaled network How is free-float defined? The amount of slack between activities The amount of slack within a path of activities The amount of slack accumulated throughout the logic network The amount of slack in a node The path with the longest sequence of activities in a project plan is called: Crises Critical Concrete Detailed        Lead-times are used to determine...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time columns in the table. Units: Time is in days, cost is in $. Activity Immediate predecessor(s) Time Cost Crash Time Crash Cost Time Reduction Cost to Crash A -- 10 5000 10 5000 B A 12 1200 11 1300 C A 11 3600 9 4800 D B 5 300 4 600 E C 8 1000 6 2000 F E 9 2400 7 5400 G...
CPM a. is a network technique that allows three time estimates for each activity in a...
CPM a. is a network technique that allows three time estimates for each activity in a project. b. assumes we do not know ahead of time what activities must be completed. c. assumes that activity time estimates follow the normal probability distribution. d. is a deterministic network technique that allows for project crashing.
The critical path for the network activities shown below is ________ with duration ________. Activity Duration...
The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 --- B 2 A C 7 -- D 4 A E 5 B,C,D
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site Selection and Preparation B D Drilling, Engineering and other Works B, C E Installation of other Equipment, Testing, and Analysis D F Project Commission and Handing over to the community E G Demonstrate safety usage and practices E, F H Preclosure safety analysis F, G 1. create an activity precedence diagram showing the network logic for each project activity you have identified; 2.    prepare...
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ____ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
1. Given is a PERT project network diagram as shown below: Activity Start A B C...
1. Given is a PERT project network diagram as shown below: Activity Start A B C D E F G H I J K End Time 0 18 24 21 38 28 34 22 20 34 34 16 0    a) The Project Completion time =   b) The Earliest Start time, ES, of Activity F =   c) The Earliest Start time, ES, of Activity K =   d) The Latest Start time, LS, of Activity E =   e) The non-critical activities...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT