Imagine US is a startup that offers high definition 3D prenatal ultrasounds for high-end customers. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parenthesis):
Activity 1: Welcome a patient and explain the procedure. (8 minutes)
Activity 2: Prep the patient (e.g., show them to the room, apply ultrasound gel). (5 minutes)
Activity 3: Take images. (14 minutes)
Activity 4: Analyze images. (10 minutes)
Activity 5: Discuss diagnostic with patient. (16 minutes)
At each location there are employees (servers) S1, S2, and S3. The assignment of tasks to servers is the following:
S1 does Activity 1 & 2
S2 does Activities 3 & 4
S3 does Activity 5
Question:
What is the capacity of this process (in customers per hour)?
Solution:
Total time taken by Server 1 (S1) is calculated as;
S1 = Activity 1 + Activity 2
S1 = 8 minutes + 5 minutes
S1 = 13 minutes
Total time taken by Server 2 (S2) is calculated as;
S2 = Activity 3 + Activity 4
S2 = 14 minutes + 10 minutes
S2 = 24 minutes
Total time taken by Server 3 (S3) is calculated as;
S3 = Activity 5
S3 = 16 minutes
The bottleneck process/server of the system = Server 2
Time taken by the bottleneck process = 24 minutes
The capacity of the process is calculated as;
Process capacity = 60 minutes / Time taken by the bottleneck process
Process capacity = 60 minutes / 24 minutes
Process capacity = 2.5 customers per hour