Panini, a popular sandwich shop offers 3 types of sandwiches (Grilled Vegetable, Grilled Chicken, and Pastrami). The below info provides demand data for each sandwich per hour:
GV: 10; GC: 15; and Pastrami: 25
There are up to 5 steps in the process of making sandwiches, listed below with activity times. Only 50% of customers want thier sanwich toasted, no matter which sandwich is ordered.
Step | GV | GC | Pastrami |
Cut Bread | .75 min | .75 min | .75 min |
Grill | 1.4 min | 1.4 min | - |
Slice Meat | - | - | 3 min |
Toast | 2 min | 2 min | 2 min |
Wrap | .5 min | .5 min | .5 min |
Suppose Panini employs 1 worker at each step. What is the highest implied utilization of this process? (HINT: find the work load per hour of each activity. Then find the implied utilization of each activity per hour.)
Time utilized in Cut bread step = 10 x 0.75 + 15 x 0.75 + 25 x 0.75
= 0.75 x 50
=37.50 minutes
Time utilized in Grill step = 10 x 1.4 + 15 x 1.4
= 1.4 x 25
= 35 minutes
Time utilized in Slice meat step = 25 x 3 = 75 minutes
Time utilized in Toast step = 10 x 2 + 15 x2 + 25 x 2
= 2 x 50
= 100 minutes
BUt only 50% gets the sandwich toasted so utilization = 50 minutes
Time utilized in Toast step = 10 x 0.5 + 15 x0.5 + 25 x 0.5
=0.5 x 50
= 25 minutes
Thus highest implied utilization of this process is on the slice meat step
and is equal to 75/60 = 1.25 or 125 %
Get Answers For Free
Most questions answered within 1 hours.