Use the table below to answer the questions
Activity |
Optimistic duration |
Pessimistic duration |
Most Likely duration |
Weighted duration |
Immediate Predecessor |
P |
15 |
27 |
21 |
- |
|
Q |
18 |
36 |
24 |
P |
|
R |
26 |
40 |
24 |
P |
|
S |
21 |
39 |
27 |
Q |
|
T |
27 |
33 |
24 |
Q,R |
|
U |
16 |
32 |
24 |
S,T |
|
V |
16 |
30 |
26 |
U |
1. Calculate the actual duration of each activity (fill-in the table)
2. Draw an AOA network diagram for the activities (in the space below):
3. State the minimum duration of the project
4. State the ES and LS time of activity T, ……………………..
(1)
Activity | Optimistic duration (a) |
Pessimistic duration (b) |
Most Likely duration (m) |
Weighted duration te = (a+4m+b)/6 |
Immediate Predecessor |
P | 15 | 27 | 21 | 21.0 | - |
Q | 18 | 36 | 24 | 25.0 | P |
R | 26 | 40 | 24 | 27.0 | P |
S | 21 | 39 | 27 | 28.0 | Q |
T | 27 | 33 | 24 | 26.0 | Q,R |
U | 16 | 32 | 24 | 24.0 | S,T |
V | 16 | 30 | 26 | 25.0 | U |
(2)
3.
Minimum duration = 123