Question

Use the table below to answer the questions Activity Optimistic duration Pessimistic duration Most Likely duration...

Use the table below to answer the questions

Activity

Optimistic duration

Pessimistic duration

Most Likely duration

Weighted duration

Immediate Predecessor

P

15

27

21

-

Q

18

36

24

P

R

26

40

24

P

S

21

39

27

Q

T

27

33

24

Q,R

U

16

32

24

S,T

V

16

30

26

U

1. Calculate the actual duration of each activity (fill-in the table)

2. Draw an AOA network diagram for the activities (in the space below):

3. State the minimum duration of the project

4. State the ES and LS time of activity T, ……………………..

Homework Answers

Answer #1

(1)

Activity Optimistic duration
(a)
Pessimistic duration
(b)
Most Likely duration
(m)
Weighted duration
te = (a+4m+b)/6
Immediate Predecessor
P 15 27 21 21.0 -
Q 18 36 24 25.0 P
R 26 40 24 27.0 P
S 21 39 27 28.0 Q
T 27 33 24 26.0 Q,R
U 16 32 24 24.0 S,T
V 16 30 26 25.0 U

(2)

3.

Minimum duration = 123

4.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use the table below to answer the questions 25 to 28. Activity Optimistic duration Pessimistic duration...
Use the table below to answer the questions 25 to 28. Activity Optimistic duration Pessimistic duration Most Likely duration Weighted duration Immediate Predecessor P 15 27 21 - Q 18 36 24 P R 26 40 24 P S 21 39 27 Q T 27 33 24 Q,R U 16 32 24 S,T V 16 30 26 U Calculate the actual duration of each activity (fill-in the table) Draw an AOA network diagram for the activities (in the space below):...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and find the critical path(s) Activities Predecessor duration A - 2 B - 10 C A 9 D A,B 7 E A,B 9 F B 5 G C 10 H D,E 1 I D,E,F 2 J F 7 K C,H,I 2 L I,J 2 M I 1 N G,K 5
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
1. Given is a PERT project network diagram as shown below: Activity Start A B C...
1. Given is a PERT project network diagram as shown below: Activity Start A B C D E F G H I J K End Time 0 18 24 21 38 28 34 22 20 34 34 16 0    a) The Project Completion time =   b) The Earliest Start time, ES, of Activity F =   c) The Earliest Start time, ES, of Activity K =   d) The Latest Start time, LS, of Activity E =   e) The non-critical activities...
The R&D Department is planning to bid on a large project for the development of a...
The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes.  The accompanying table shows the activities, times, and sequences required: Activity Immediate Predecessor Optimistic Most Likely Pessimistic A - 3 6 8 B A 2 4 4 C A 1 2 3 D C 6 7 8 E B,D 2 4 6 F B 6 10 14 G E, F 1 2 4 H F 3 6 9 I...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT