Question

You have been assigned to manage a time-constrained project. The project absolutely must be finished by...

You have been assigned to manage a time-constrained project. The project absolutely must be finished by the customer-imposed deadline. No exceptions will be made, even if it means additional expenses must be incurred. As the project manager, you are busy developing the project schedule and budget. You notice that the demand for a particular resource, XT-002 Deconstructor, varies greatly over the course of the project. In an attempt to make an optimal project schedule, which of the following methods should you use to manage the XT-002 resource?
A. Smooth the demand for XT-002 to minimize fluctuations
B. Use the parallel method to schedule activities with resource constraints in mind
C. Remove all activities that use XT-002 from the project
D. Add optional overtime for all workers assigned to the project

Homework Answers

Answer #1

Option A is the answer as this is a time-constrained problem and in time constrained problems resource smoothing is used to smooth the demand and ensure that the project is completed on time.

The option B cannot be used because using the parallel method to schedule activities with resource constraints in mind would lengthen the time of the project which is not possible as the project has strict timelines.

Options C and D are eliminated because they would increase the cost and removing all activities is also not an option.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The PM for the web project left and you have been assigned to manage the project....
The PM for the web project left and you have been assigned to manage the project. The PERT for this project is 30 days and the variance is +/-5 days. There are too many activities on the critical path. The Early Start for task A on the critical path is day 5 and the Late Start is day 7, the Early Finish is day 10, and the Late Finish is on day 15. The CPI is 0.5, but the SPI...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Week 1 Project Instructions Supply and Demand Concepts You have been hired by a new firm...
Week 1 Project Instructions Supply and Demand Concepts You have been hired by a new firm selling electronic dog feeders. Your client has asked you to gather some data on the supply and demand for the feeder, which is given below, and address several questions regarding the supply and demand for these feeders. Price per Feeder Quantity Demanded Quantity Supplied $300 500 1800 270 600 1700 240 700 1600 210 800 1500 180 1000 1400 1150 1100 1300 120 1200...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT