You have been assigned to manage a time-constrained project. The
project absolutely must be finished by the customer-imposed
deadline. No exceptions will be made, even if it means additional
expenses must be incurred. As the project manager, you are busy
developing the project schedule and budget. You notice that the
demand for a particular resource, XT-002 Deconstructor, varies
greatly over the course of the project. In an attempt to make an
optimal project schedule, which of the following methods should you
use to manage the XT-002 resource?
A. Smooth the demand for XT-002 to minimize fluctuations
B. Use the parallel method to schedule activities with resource
constraints in mind
C. Remove all activities that use XT-002 from the project
D. Add optional overtime for all workers assigned to the
project
Option A is the answer as this is a time-constrained problem and in time constrained problems resource smoothing is used to smooth the demand and ensure that the project is completed on time.
The option B cannot be used because using the parallel method to schedule activities with resource constraints in mind would lengthen the time of the project which is not possible as the project has strict timelines.
Options C and D are eliminated because they would increase the cost and removing all activities is also not an option.