Question

QUESTION 2. The following table explain the logical relationship of activities of a given project, including...

QUESTION 2. The following table explain the logical relationship of activities of a given project, including the duration in weeks of each activity.

Activity

Follows

Duration (Weeks)

M

G, F

4

F

Start

6

G

Start

3

D

Start

7

K

D, G

5

L

K, J

8

J

D

3

S

L, M, F

4

Finish

S

  1. Draw the network
  2. Perform the forward path as determine the project duration (5 Marks)
  3. Perform the back path and determine the critical path (5 Marks)

Homework Answers

Answer #1

a. Network Diagram

b. Project Duration : 24 Days

ES = Earliest Start, EF = Earliest Finish, LS = Latest Start, LF = Latest Finish

Forward Path:

Activities F,G,D has no any predecessor so all these activities start on Day 0.

ES =0, EF = Project Duration

For all other activities

E: (ES, EF)
ES = Latest Earliest Finish time of predecessors.

EF = ES + Duration

c. Critical path: D-K-L-S

Backward Path:

L: (LS, LF)

LF = Lowest Latest Start time (LS)  of Following activities.

LS = LF - Project Duration

Activity S is the last activity in the project so for S, LS= ES and LF = EF.

S has three predecessors F, M and L

LF for M = LS for S  = 20

LS for M = 20 - 4 = 16

LF for F = min (LS for S or LS for M) = min (20,16) = 16

LS for F = 16-6 =10

LF for L = LS for S = 20

LS for L = 20-12 =8

Now, L had two predecessors K and J

LF for K = LS for L = 12

LS for K = 12-5 = 7

LF for J = LS for L =12

LS for J = 12-3 =9

Now for remaining two activities D & G.

LF for D = min (LS for K, LS for J) = 7

LS for D = 7-7 =0

LF for G = min(LS for M, LS for K) = 7

LS for G = 7-3 =4.

All activities are critical for which ES = LS.

In this project, D K L and S are critical activities.

And Critical Path = D-K-L-S

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D C 1 5 E B 2 5 F E 8 5 G D 10 5 H B 2 5 I B 3 5 J F,G,I 3 5 K H 2 5 L J,K 3 5 M L 1 5 i.Construct an activity on the arrow network ii. Determine the Duration of the Critical Path; iii. Draw the corresponding Gantt chart iv. Draw the resource...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can start at the same time, however Activity C can only start once Activity A ends Activity D can only start once Activity B and Activity C ends Activity E and Activity F can only start once Activity D ends The following table shows Durations for each activity Activity Duration (weeks) A 5 B 4 C 2 D 7 E 3 F 2 a. Draw...
Given below are the durations of and the precedence relationships among the activities required to compute...
Given below are the durations of and the precedence relationships among the activities required to compute a project. 1) construct an AOA network of the project 2)what is the critical path? determine the expected duration of the project. 3)compute the standard deviation of the critical path Duration(days) Activity pre-decessor(s) a m b A - 4 7 12 B A 6 9 13 C A 5 7 9 D B,C 3 5 8 E B 7 8 10 F A 2...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above Reset Selection Question 9 of 21 Which of the following is NOT included in project control? A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. All of the above are included Reset Selection Question 10 of 21...
Below are the project steps for the creation of a television advertisement for Foolio, which is...
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created.    Consider the following data for questions 1 through 5: Activity Duration (days) Description Preceding Activity(ies) A 6 Create script for advertisement - B 4 Book technical crew A C 4 Book actors A D 3 Create props and costumes B,C E 6 Book location C F 5 Filming and editing D,E How many paths...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and find the critical path(s) Activities Predecessor duration A - 2 B - 10 C A 9 D A,B 7 E A,B 9 F B 5 G C 10 H D,E 1 I D,E,F 2 J F 7 K C,H,I 2 L I,J 2 M I 1 N G,K 5
A project manager, in preparation for the construction of roads, has identified the activities and their...
A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table). Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D J 3 F K 8 E,H L 4 C,J (a) How long the project will take? (b) State the critical activities. (c)...