QUESTION 2. The following table explain the logical relationship of activities of a given project, including the duration in weeks of each activity.
Activity |
Follows |
Duration (Weeks) |
M |
G, F |
4 |
F |
Start |
6 |
G |
Start |
3 |
D |
Start |
7 |
K |
D, G |
5 |
L |
K, J |
8 |
J |
D |
3 |
S |
L, M, F |
4 |
Finish |
S |
a. Network Diagram
b. Project Duration : 24 Days
ES = Earliest Start, EF = Earliest Finish, LS = Latest Start, LF = Latest Finish
Forward Path:
Activities F,G,D has no any predecessor so all these activities start on Day 0.
ES =0, EF = Project Duration
For all other activities
E: (ES, EF)
ES = Latest Earliest Finish time of predecessors.
EF = ES + Duration
c. Critical path: D-K-L-S
Backward Path:
L: (LS, LF)
LF = Lowest Latest Start time (LS) of Following activities.
LS = LF - Project Duration
Activity S is the last activity in the project so for S, LS= ES and LF = EF.
S has three predecessors F, M and L
LF for M = LS for S = 20
LS for M = 20 - 4 = 16
LF for F = min (LS for S or LS for M) = min (20,16) = 16
LS for F = 16-6 =10
LF for L = LS for S = 20
LS for L = 20-12 =8
Now, L had two predecessors K and J
LF for K = LS for L = 12
LS for K = 12-5 = 7
LF for J = LS for L =12
LS for J = 12-3 =9
Now for remaining two activities D & G.
LF for D = min (LS for K, LS for J) = 7
LS for D = 7-7 =0
LF for G = min(LS for M, LS for K) = 7
LS for G = 7-3 =4.
All activities are critical for which ES = LS.
In this project, D K L and S are critical activities.
And Critical Path = D-K-L-S
Get Answers For Free
Most questions answered within 1 hours.