Question

The estimated time for the critical path is 44.5 weeks. ?The activity variance along the critical...

The estimated time for the critical path is 44.5 weeks.

?The activity variance along the critical path is 22.027 weeks.

?f) The probability that Hopkins Hospitality will finish the project in 40 weeks or less is ?

?(Enter as a probability and round your response to three decimal? places.)

Homework Answers

Answer #1

The estimated time for the critical path = m = 44.5 weeks

Variance of the critical path = 22.027 weeks

Therefore, standard deviation of the critical path = Sd = Square root ( 22.027 ) = 4.693 weeks

Let Z value for the probability that the project will finish in 40 weeks or less = Z1

M + Z1 x sd = 44

Or, 44.5+ 4.693.Z1 = 40

Or, 4.693.Z1 = - 4.5

Or, Z1 = - 0.9588 ( - 0.96 rounded to 2 decimal places )

Corresponding probability for Z = - 0.96 as derived from standard normal distribution table is 0.16853 ( 0.168 rounded to 3 decimal places )

PROBABILITY THAT THE HOPKINS HOSPITAL WILL FINISH THE PROJECT 40 WEEKS OR LESS = 0.168

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8 13 B 5 7 9 C 5 12 19 D 2 5 8 E 5 9 19 F 4 8 18 G 9 15 21 H 4 6 14 If required, round your answers to two decimal places. A.) Find the critical path. Activity Expected Time Variance A B C D E F G H Earliest Latest Earliest Latest Critical Activity Start Start Finish...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion time of the critical path? What is the...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the...
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks ) Immediate Time (weeks ) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 44 88 1010 long dash— G 22 33 44 C, E B 22 99 2424 A H 22 22 22 F C 99 1212 1616 A I 77 77 77 F D 44 66 99 A J 44 77...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Which of the following statements is true? Group of answer choices 1)The variance of the time...
Which of the following statements is true? Group of answer choices 1)The variance of the time taken to complete an activity is equal to (b − a)/6. 2)The critical path is the path with the largest probability of being completed on time. 3)The standard deviation of a project completion time is the sum of the standard deviations for the critical path activities. 4)Three time estimates are necessary so that we can estimate the parameters of the Beta distribution. thanks
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
The information for project X is shown below. What are the critical path and the completion...
The information for project X is shown below. What are the critical path and the completion time of the project? Crashing Costs Activity Preceding Normal Time 1st Week 2nd Week K — 8 weeks $4100 — L K 6 weeks 3250 — N K 1 week 450 450 M L 5 weeks 3000 3500 J N 4 weeks 500 — Q J,M 6 weeks 4000 4000 KLMQ, 25 weeks KLNMJQ: 25 weeks KNJQ, 25 weeks KNJQ, 30 weeks KLMQ, 30...