Question

Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on...

Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2). The processing times are given in the table below.

Job

Machine 1

Machine 2

L

10

2

M

5

4

N

7

5

O

3

6

P

1

7

** Please show excel steps so i can see if I did this right** thanks

  1. What is the optimal sequence?

  2. What is the total flow time for this sequence?

Homework Answers

Answer #1

Answer

  • What is the optimal sequence? - P , O , N , M L
  • What is the total flow time for this sequence? - 26 hours

Pls. see the details below:

Processing times
Job Machine 1 Machine 2
L 10 2
M 5 4
N 7 5
O 3 6
P 1 7
look for the lowest time 1 =MIN(B3:C7)
which is Job P Machine 1
Next step
Look for next min out of L M N O 2 =MIN(B3:C6)
which is Job L Machine 2
so we place it at the end as Machine 2
Next step
Look for next min out of M N O 3 =MIN(B4:C6)
which is Job O Machine 1
so place at the 2nd position
Next step
Look for next min out of M N 4
which is Job M Machine 2
so placed at 2nd last position
Optimal sequence is
P,O,N, M,L
Optimal Sequence
P O N M L
  • Total flow time of the sequence is 26 hours as I have placed the optimal sequence in order in an excel and job L finally end at Machine 1 at 26 hours
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Machine 1 P O N M L
Machine 2 P O N M L

Excel

If you liked my answer thumbs up pls.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.] Five jobs arrived to be processed with the processing times and due dates. Present Date= 300 Work Order A B C D E Processing Times (Days) 14 5 40 12 7 Due Date 167 163 195 191 161 . . . Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the...
What is the optimum job sequence for the jobs listed below using Johnson's Rule? Processing time(hrs)...
What is the optimum job sequence for the jobs listed below using Johnson's Rule? Processing time(hrs) Job Center 1 Center 2 d 13 23 e 23 14 f 16 18 g 20 17 A. e-g-f-d B. d-g-f-e C. d-f-g-e D. e-d-f-g E. f-e-d-g
Consider a machine where jobs are being processed. The mean production time is 6 minutes and...
Consider a machine where jobs are being processed. The mean production time is 6 minutes and the standard deviation is 2 minutes per job. The mean number of jobs arriving per hour is 7. Suppose that the inter-arrival times are exponentially distributed. Determine the mean waiting time of the jobs._______ minutes What fraction of the time is the machine idle?________ What is the average time for a job to be completed?________ minutes
You have been asked to sequence the following jobs. Task A must always be done before...
You have been asked to sequence the following jobs. Task A must always be done before Task B. Using Johnson's Rule, in what order will you do the jobs? Job Task A Task B A 3 6 B 7 6 C 5 2 D 5 8 E 4 7 F 9 3 G 1 4
RESTORE machine shop makes customized replacement parts for older equipment. All customer jobs listed must be...
RESTORE machine shop makes customized replacement parts for older equipment. All customer jobs listed must be machined first, then polished. Determine the optimal processing sequence of the six jobs listed below. Jobs Machining Hrs Polishing Hrs A 5 4 B 7 3 C 3 2 D 4 1 E 1 2 F 3 4 job A is finished at time 21 11 9 13
Three jobs are to be assigned to three machines. Cost for each job-machine combination appears in...
Three jobs are to be assigned to three machines. Cost for each job-machine combination appears in the table below. Perform the assignment method. What is the optimal assignment? Machine A Machine B Machine C Job 1 11 14 6 Job 2 8 10 11 Job 3 9 12 7
Part 4.   Questions 6,7. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs...
Part 4.   Questions 6,7. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.] The jobs A,B,C,D,E, arrived in that order to be processed on two machines. Job A B C D E Time on Machine 1 45 53 63 31 75 Time on Machine 2 42 65 61 53 77 Question 6. Which is the Johnson’s Rule schedule?      (A) ‘ACEBD’     (B) ‘DCABE’     (C) ‘DBECA’     (D) ‘DABEC’   (E) none...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT