Question

Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine...

Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine activities involved. These activities have been labeled A through I in the following table. The company is planning to finish the project in 34 weeks. Please answer the following questions.

  1. Determine the expected (estimated) duration and variance for each activity. You can round the expected duration numbers without decimals.

Activity

Immediate

Predecessor(s)

Optimistic

Probable

Pessimistic

Expected duration

Variance

A

--

5

9

13

Answer

Answer

B

--

3

3

9

Answer

Answer

C

--

6

9

15

Answer

Answer

D

A,C

5

7

12

Answer

Answer

E

B

4

6

14

Answer

Answer

F

C,B

3

4

8

Answer

Answer

G

D

4

4

4

Answer

Answer

H

E,F

2

4

9

Answer

Answer

I

G,H

7

10

13

Answer

Answer

2. Draw the network diagram in a page and then fill the below table:

Activity

Early Start

Early Finish

Late Start

Late Finish

Slack

A

Answer

Answer

Answer

Answer

Answer

B

Answer

Answer

Answer

Answer

Answer

C

Answer

Answer

Answer

Answer

Answer

D

Answer

Answer

Answer

Answer

Answer

E

Answer

Answer

Answer

Answer

Answer

F

Answer

Answer

Answer

Answer

Answer

G

Answer

Answer

Answer

Answer

Answer

H

Answer

Answer

Answer

Answer

Answer

I

Answer

Answer

Answer

Answer

Answer

3. What is the critical path? Draw the network carefully in a page to make the correct sequence of the critical path.

4.

A) What are the project variance and the project standard deviation?

B) What is the probability that the project will be finished in less than 40 weeks?

Homework Answers

Answer #1

1.

Activity Predecessor Opt Probable Pessi Expected Variance
A - 5 9 13 9 1.78
B - 3 3 9 4 1.00
C - 6 9 15 9.5 2.25
D A,C 5 7 12 7.5 1.36
E B 4 6 14 7 2.78
F C,B 3 4 8 4.5 0.69
G D 4 4 4 4 0.00
H E,F 2 4 9 4.5 1.36
I G,H 7 10 13 10 1.00

te = (to + 4tm + tp)/6

te = expected time
to = optimistic time
tm = probable time
tp = pessimistic time

variance = (tp - to)^2/36

The network diagram is drawn with following terminology:

ES Sla EF
Act
LS Dur LF

where Act is activity, Dur is duration, ES and EF are earliest start and finish times and LS and LF are latest start and finish times and Sla is slack time calculated as LS-ES

The ES and EF are calculated in the forward path. For activities A, B and C , ES is 0 and EF is ES + duration i.e. 9, 4 and 9.5 respectively. Further, the ES for E is EF for B i.e. 4 and hence EF for B is 4+7=11. For F, the ES will be maximum EF of B and C i.e. 9.5 hence EF for F will be 14. Similarly we reach the last activity I with ES being maximum EF of G and H i.e 21. Hence EF for I will be 21+10 = 31 which is the project completion time

To calculate LS and LF we start backwards from I. Here LF will be 31 and LS will be LF-duration i.e. 21. Next LF for both G and H will be LS for I i.e. 21. Hence LS for G and H will be 17 and 16.5 respectively. Further, for activity C, the LF will be minimum LS of D and F i.e. 9.5. Hence LS for C will be 0.

Finally we calculate slack time for all using the formula LS-ES

2. The summary of ES, EF, LS, LF and slack is given below

Activity ES EF LS LF Slack
A 0 9 0.5 9.5 0.5
B 0 4 5 9 5
C 0 9.5 0 9.5 0
D 9.5 17 9.5 17 0
E 4 11 9 16.5 5
F 9.5 14 12 16.5 2.5
G 17 21 17 21 0
H 14 18.5 16.5 21 2.5
I 21 31 21 31 0

3. From the diagram above, the path in which the activities have a slack of zero is the critical path. The same is highlighed in RED. i.e. path C-D-G-I that takes 31 weeks

4.

A. The project variance is the sum of variance of activities on the critical path i.e C,D,G and I = 2.25+1.36+0+1 = 4.61

Hence project standard deviation = sqrt of variance = 2.14735

B. For project completion in less than 40 weeks, we need to calculate z statistic

z = (x-u)/SD

where x = 40, u = 31 and SD = 2.14735

Hence z = 4.191213

To calculate the probability, we need to refer to standard normal table or use normsdist(z) function in excel that gives 0.9999

i.e. there is a 99.99% probability of the project finishing in less than 40 weeks

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including the duration in weeks of each activity. Activity Follows Duration (Weeks) M G, F 4 F Start 6 G Start 3 D Start 7 K D, G 5 L K, J 8 J D 3 S L, M, F 4 Finish S Draw the network Perform the forward path as determine the project duration (5 Marks) Perform the back path and determine the critical...
Below are the project steps for the creation of a television advertisement for Foolio, which is...
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created.    Consider the following data for questions 1 through 5: Activity Duration (days) Description Preceding Activity(ies) A 6 Create script for advertisement - B 4 Book technical crew A C 4 Book actors A D 3 Create props and costumes B,C E 6 Book location C F 5 Filming and editing D,E How many paths...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There can be multiple critical paths on the same project, all with different durations. B) The early finish of an activity is the latest early start of all preceding activities. C) The late start of an activity is its late finish plus its duration. D) If a specific project has multiple critical paths, all of them will not have the same duration. E) B) and...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above Reset Selection Question 9 of 21 Which of the following is NOT included in project control? A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. All of the above are included Reset Selection Question 10 of 21...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8 13 B 5 7 9 C 5 12 19 D 2 5 8 E 5 9 19 F 4 8 18 G 9 15 21 H 4 6 14 If required, round your answers to two decimal places. A.) Find the critical path. Activity Expected Time Variance A B C D E F G H Earliest Latest Earliest Latest Critical Activity Start Start Finish...
Given below are the durations of and the precedence relationships among the activities required to compute...
Given below are the durations of and the precedence relationships among the activities required to compute a project. 1) construct an AOA network of the project 2)what is the critical path? determine the expected duration of the project. 3)compute the standard deviation of the critical path Duration(days) Activity pre-decessor(s) a m b A - 4 7 12 B A 6 9 13 C A 5 7 9 D B,C 3 5 8 E B 7 8 10 F A 2...